The renovated Vác-Diósjenő railway line will open within days
Another phase of work has been completed on the country's busiest branch line. We last reported on this in mid-December reported on the modernisation work being carried out on the Vác–Balassagyarmat railway line, number 75, MÁV. Zsolt Hegyi, CEO of the MÁV group, recently published another photo report Facebook page. He reported:
From Saturday, 3 January, train services will resume as scheduled between Vác and Diósjenő.
Testing will continue on the track until Friday.
Zsolt Hegyi explained that a significant portion of the work on the Vác–Diósjenő section had already been completed before Christmas. Subsequently, the track and safety equipment were checked using a measuring train, and test operations are currently underway until Friday: the renovated section is being inspected using a Bz motor train consisting of several carriages, without passengers.
The purpose of test runs is to verify that the line is safe and reliable in all respects at the authorised track speed.
As is well known, in September 2025, a Bz-type motor train derailed on the line at Magyarkút, and experts decided not only to repair the accident site, but also to carry out comprehensive work on the branch line.
Source: Link
-
Current at 2026. 06. 01.
The M5 motorway is in tatters – can the M6 save the day?
-
Industry news 2026. 06. 02.
The domestic construction industry could see a boost – there is potential to unlock €16.4 billion in EU funding
-
Current at 2026. 06. 01.
Project KÉSZ Csoport has refurbished six treatment rooms at Bethesda Children’s Hospital
-
Climate-X 2026. 06. 02.
Who is taking the lead in the construction industry’s green transition?