The railway line running through South Somogy is to be upgraded: the search for a contractor is already underway

Published

illustration – Tamás Andrónyi/magyarepitok.hu
Due to the poor condition of the track, the No. 60 railway line has recently been affected by significant delays and reduced speeds.

A railway line running through the picturesque countryside of Somogy is to be upgraded: a contractor is already being sought to carry out the refurbishment of the section of Line 60 between Gyékényes and Berzence, and between Középrigóc and Darány (which, amongst other places, passes through the ancient juniper forest near Barcs).

Railway Line 60, which connects Murakeresztúr with Szentlőrinc, is a single-track line; these sections are not electrified and are typically served by the Pannónia InterRégió (Szombathely–Nagykanizsa–Pécs) and local multiple units. The original authorised track speed is 80 km/h, but due to the poor condition of the track, there have been significant delays and speed restrictions recently.

A total of 12,350 reinforced concrete slabs are being replaced

In line with the above, the aim of the investment is to restore the line’s original authorised speed of 80 km/h and to improve timetable reliability. According to MÁV’s previously announced plans, 3 billion forints has been earmarked for this project alone, and a significant improvement in transport reliability is expected as a result of the development.

According to the recently published public procurement notice, a total of 12,350 reinforced concrete sleepers will be replaced during the works, in addition to installing continuous welded rail, replacing rails and carrying out ballast screening.

Here are the details

On the section between Gyékényes and Berzence, in addition to replacing 9,450 concrete sleepers, ballast screening is being carried out over a distance of 15.6 kilometres, and 259 rails, each 120 metres long, are being laid.

The work to be carried out between Középrigóc and Darány includes the replacement of a further 2,900 sleepers, the screening of 5.65 kilometres of track bed, and the installation of 95 new rails. On the latter section, 200 metres of substructure repairs and the refurbishment of the insulation on three structures, totalling 52.8 square metres, must also be carried out.