Bound track
After more than half a century, Budapest’s busiest railway approach section is being upgraded
MÁV is to receive an additional ten billion forints in funding for the refurbishment of the Budapest approach section of the Cegléd main line, the Minister for Transport and Investment announced on his Facebook page. Dávid Vitézy signed the grant agreement on 16 November for the refurbishment of the Budapest approach section of the Cegléd main line. MÁV had previously conducted two successful public procurement procedures. We reported on these previously, with the construction work being carried out by Swietelsky Vasúttechnika Kft. specialists. The winning bids were below the estimated value, so the contractor will be able to carry out the work for a total of 9.6 billion forints net.
More than two hundred trains run on the five-kilometre stretch every day
In his post, the minister noted that the affected section of railway line 100a, leading to Nyugati railway station, was last comprehensively refurbished in the early 1970s. A significant part of the track was built in the 1940s and runs on an embankment 4–5 metres high. More than two hundred passenger and freight trains pass through this five-kilometre section every day. Due to the condition of the track, trains are restricted to speeds of just 40–60 kilometres per hour in several places, instead of the permitted 80.
The contractor is carrying out a complete replacement of the track superstructure over 12,338 metres of track. New overhead lines are also being installed over a distance of nearly 15 kilometres. Maintenance work is being carried out on fourteen railway structures; embankments and bridge insulation are being repaired, and telecommunications and signalling cables are being replaced where necessary. The major refurbishment will require track closures, and passengers will be provided with detailed information in advance.
Plans are afoot for a new flyover in Kőbánya-Kispest and a new exit in Zugló
In Kőbánya-Kispest, 6,000 tonnes of crushed stone and 1,250 concrete slabs are being used for the maintenance work currently underway. Preparatory work is also under way in connection with the new Kőbánya-Kispest overpass, which will feature lifts and escalators, and the insulation and refurbishment of the existing platform roofs; In Zugló, plans are in place for accessible platform connections and a new exit onto Szugló Street, whilst work is also underway on the refurbishment and accessibility improvements to the lower building at Kőbánya. According to the minister, the MÁV-csoport’s 2027 renovation budget, which has been increased from 30 to 80 billion forints, will enable works of this scale.
Source: Link
-
Road building 2026. 10. 13.
A consortium comprising STRABAG and Duna Aszfalt has been awarded the contract to build the North Macedonian motorway
-
Current at 2026. 10. 17.
Young skilled workers can set off on their apprenticeship placements today as well
-
Current at 2026. 10. 13.
It’s time to provide information to those in the sector – that’s what this year’s Építőipar Summit was all about
-
Industry news 2026. 10. 18.
The road construction sector celebrated its half-century anniversary in Eger