Road building
Celldömölk’s main road is being upgraded with a rain garden, a turning lane and a well-maintained pavement
An important road in Celldömölk town centre is set to undergo a comprehensive reconstruction: Szomraky Street is to be refurbished along its entire length – some 527 metres – by Colas based on plans drawn up by Zala West-Plan Bt.. It was not only the ageing road surface but also subsidence in the sub-base layers and inadequate drainage that made the reconstruction necessary on this busy street in the town in Vas County, which provides access to numerous public institutions.
The street is being renovated along its entire length
Work commenced in accordance with the temporary traffic management plan drawn up by B-THERV Statik Bt., starting with a condition survey and levelling. The road surface is being resurfaced using different techniques on the various sections: on the first 190 metres, cement-based remix technology is being used to reinforce the deeper layers – which creates a new load-bearing base after the old layers have been milled off – whilst the remaining section is being milled to profile. Following this, two layers of new asphalt will be laid uniformly across both sections.
As part of the project, 4,580 square metres of road and 450 square metres of pavement will be resurfaced. This will require around 1,250 tonnes of asphalt.
A rain garden and a turning lane will also be built
One of Colas’s key tasks was the precise design of the gradients and drainage, as the connecting levels and the stormwater channel meant that the contour lines could hardly be altered.
Traffic flow will be improved by the reconstruction of the Sági utca junction, where the road surface will be widened to create a dedicated turning lane, expanding the junction to three lanes to facilitate turning from Szomraky utca. Alongside the comprehensive reconstruction of the connecting pavements, three new cobbled car parks will be built, whilst the surfacing of the existing ones will be improved and kerb cuts will be installed at accessible parking spaces.
A rain garden is also being built on the western side of the former Benedictine monastery. Across the 415-square-metre area, Leier Castrum paving stones and water-permeable TerraWay paving will line the walkways, which will be home to nearly 2,300 biodiverse perennial plants.
Special attention will be paid to the 37 large plane trees in the area, which will undergo maintenance pruning and thinning; on six of these trees, a structural crown stabilisation system will also be installed with the assistance of a qualified arborist. The street lighting will also be modernised by relocating two lampposts and replacing seven lamp heads.
They’re building with virtually no storage facilities
In the narrow city centre street, no loose materials are left lying about, and the demolition rubble is transported immediately to Jánosháza for recycling. The team from Colas Út team, which is carrying out the works, uses its own fleet of machinery to perform the remixing, milling and asphalting tasks, whilst coordinating the work of subcontractors for the remaining tasks; as a result, a team of 30–35 specialists is present on site during peak periods. The aim is to ensure that all weather-sensitive work is completed before the onset of frost.
The contractor took over the site on 4 September, and the entire project is expected to be completed by 15 December 2026.
Source: Link
-
Road building 2026. 10. 13.
A consortium comprising STRABAG and Duna Aszfalt has been awarded the contract to build the North Macedonian motorway
-
Current at 2026. 10. 10.
„The focus will not be on Lean’s equipment, but on how we operate” – the ‘Lean in the Construction Industry’ conference in November
-
Current at 2026. 10. 17.
Young skilled workers can set off on their apprenticeship placements today as well
-
Current at 2026. 10. 13.
It’s time to provide information to those in the sector – that’s what this year’s Építőipar Summit was all about