Bound track

A new public procurement process is being prepared to continue the second phase of the Déli körvasút

Published

Photos: Illustration / magyarepitok.hu archive / Mihály Nagy
Preparations are beginning for the termination of the construction contract relating to Phase II of the Déli körvasút and for the new public procurement process. MÁV Pályaműködtetési Zrt. must submit its tender strategy for approval by 30 November, whilst a project steering committee chaired by a minister will be formed to oversee the strategic management of the project.

An order laying the groundwork for the continuation of capacity expansion on the Ferencváros–Kelenföld railway line was published on Thursday in the Official Gazette. The decree issued by Dávid Vitézy, Minister for Transport and Investment, governs the preparation of contract closure, new public procurement, project management and operational tasks for Phase II of the Southern Circular Railway.

The directive, which comes into force on 13 November, covers the termination and closure of the current works contract, the preparation of one or more new public procurement procedures to implement the project, and ensuring the continuity of EU funding.

 

They assess the work carried out and prepare the financial accounts

The termination of the contract and its technical and financial closure are prepared and carried out by the State Secretary for Public Administration and the State Secretary responsible for public transport and railways, with the assistance of MÁV Pályaműködtetési Zrt. (MÁV PM).

They must carry out the task as quickly as possible, in a lawful and economically justifiable manner, whilst ensuring the continuity of the project.

As part of this, the technical condition of completed, ongoing and uncompleted works is assessed, the financial accounts are finalised, and any potential litigation claims and dispute resolution risks are identified. An action plan is also drawn up setting out the tasks involved in the termination and closure of the project.

It is also the responsibility of MÁV PM to ensure that the technical scope, timetable and use of the worksite for the current project and the next phase of the Déli körvasút remain coordinated even during the termination of the contract.

There are four months available to compile the new tender documentation

The directive also designates MÁV PM to prepare and conduct the new public procurement procedure. The company must submit the tender strategy to the Minister for approval by 30 November, and must compile the full public procurement documentation within four months of the termination of the current contract.

The conditions for initiating the procedure are ministerial approval of the tender strategy, the completion of preliminary legal, public procurement and financial checks, confirmation that the necessary funds are available, and clarification of the financing terms.

In connection with the new public procurement process, steps must also be taken to ensure that EU funding is maintained. The Deputy State Secretary responsible for the coordination of European Union affairs is responsible for the measures required to this end, in coordination with the preparations for the termination of the contract and the development of the new procedure. For the strategic management of the investment, the Southern Circular Railway Project Management Committee (PIB) will be established, chaired by the Minister.

 

Transparent public procurement would secure EU funding

Dávid Vitézy announced on 9 October that the Közlekedési és Beruházási Minisztérium was suspending the Déli körvasút project and excluding Lőrinc Mészáros’s railway construction company, V-Hidat, from the ongoing railway construction works. According to its statement, attempts were once again made to submit tenders in connection with projects designed and prepared by the Kontúr Csoport. The Déli körvasút project was also designed by the Kontúr Csoport, one of Hungary’s largest railway design firms, which was acquired by Lőrinc Mészáros.
According to the minister’s statement, there are serious grounds for suspecting that unlawful collusion took place during the public procurement process for the construction contract. He claimed that V-Híd had gained access to documents prepared by the Kontúr Csoport, thereby gaining a competitive advantage that renders the public procurement process unlawful. According to Dávid Vitézy, following these findings, the Európai Bizottság informed Hungary that it would withdraw all EU funding from the project.
According to the minister, there are two options left: either the project continues with Hungarian state funding, or the contract with the current contractor is terminated and a new, „fair and transparent” public procurement procedure is launched, in which EU funds may once again become available.

Source: Link

Popular