The River Charles posed no obstacle either – the M1 bridge is being rebuilt 1 metre higher

Published

Photos: MKIF
Despite having to contend with mud and rain, the girders of the new bridge spanning Railway Line 5 were hoisted into place on the M1 motorway.

In several places, a month’s worth of rainfall fell on the land last week due to Cyclone Charles, but whilst this is a blessing for agriculture, it may not necessarily be welcome news for those in the construction industry. Reporting on the expansion of the M1 motorway, MKIF also highlighted in its latest post that the contractors were working under exceptional circumstances in the early hours from Thursday to Friday.

It was then, in the pouring rain, that the bridge girders were lifted into place with millimetre precision in the Csém area, above Railway Line No. 5. „Although the mud and rain made the work more difficult, thanks to the well-prepared team and their coordinated efforts, the tasks were still carried out according to plan,” the post emphasised.

We must take the forthcoming development into account

The MKIF had already reported on the construction of this very bridge back in May. The structure has a span of 56 metres and consists of two large beam sections: the first weighs 27.5 tonnes; the second weighs 26 tonnes.

Whilst also outlining the background to the sub-project, they revealed that the railway line linking Székesfehérvár and Komárom is not currently electrified; however, during the expansion of the M1 motorway, the investor MKIF must take this future development into account.

Accordingly, the new bridge will be approximately 1 metre higher than the current bridge. This will ensure that, should any future railway development take place, the overhead line will fit beneath the bridge.