Work is already underway on laying the temporary asphalt layers on the section of the M1 motorway expansion project in the Nagyegyháza area. The aim of the traffic management measures is to ensure that traffic flows in both directions throughout the entire construction period...
Making the previously demolished border crossing point accessible will require a significant investment: in the first phase, 1.2 km of motorway will be built, followed by, among other things, a road overpass, a comprehensive service area and a service building.
The radars monitor traffic in real time and automatically adjust the traffic signals if there is a risk of congestion.
A total of 72 bridges and overpasses are being rebuilt or renovated along the 78-kilometre stretch of motorway.
The MKIF has begun work on the construction of the new M1 junction by milling away the wearing course, binder course and base course.
Work is in full swing on the Biatorbágy section of the M1 motorway, where the entire road structure is currently being dismantled and rebuilt as part of the expansion. On the side heading towards Budapest, work is underway...
The operation of the domestic motorway network today involves much more than just maintenance. Digital data collection, artificial intelligence, drone technology and sustainability considerations are shaping the future. We spoke to two young professionals...
The work is already visible from the track: the concrete work on the structural beams for the future western and eastern collection and distribution tracks is in full swing.
The MKIF podcast channel, titled „We’re on Track”, features several regular segments covering a variety of topics. László Szimicsku, Director of Communications, answers the most interesting and important questions from passengers on a monthly basis.
This latest episode highlights the most exciting aspects of the complex development.