What is being built?

The reinforced concrete tower of the Mohácsi Nemzeti Emlékhely, which tapers towards the top, was built using a bespoke formwork solution

Published

Photos: PERI
Walls over five metres high, cast in a single pour, 40-centimetre-thick floor slabs and a chapel tower tapering towards the top made the reconstruction of the Mohácsi Nemzeti Emlékhely a technically complex project. The reinforced concrete structures were constructed by SH-BAU Mérnöki Kft., whilst PERI contributed to the project by providing formwork and scaffolding systems, as well as technical support.

To mark the 500th anniversary of the Battle of Mohács, a large-scale reconstruction took place at the Mohács National Memorial Site. In addition to the new exhibition space, which is partly below ground level, a reception building, a chapel and an ossuary were constructed, with the volume of concrete used in the new structures exceeding 5,200 cubic metres. In this article, we outline the structural and formwork challenges involved in realising the unique geometries and architectural elements.

 

Photos: PERI

 

Several different types of structure were combined in a single project

PERI contributed to the project by providing the formwork, scaffolding and engineering solutions required for the construction of reinforced concrete structures. The company’s engineers prepared the designs, material specifications and structural calculations for the construction of the reception building, the partially underground exhibition space, the chapel and ossuary, and the approximately 16-metre-high reinforced concrete chapel tower.

One of the main engineering challenges of the project was that structures that differed significantly from one another were involved in the development.

The partly underground, heavy reinforced concrete sections of the building required substantial support; geometric precision was crucial for the arched walls, whilst a bespoke solution had to be devised for the chapel tower due to its variable geometry and great height.

 

 

Five-metre-high walls cast in a single pour

For the reinforced concrete walls, the PERI TRIO framed wall formwork system was primarily used. The system’s load-bearing capacity made it possible to cast walls up to 5 metres high in a single pour, without the need for any special additional solutions.

To construct the curved walls, RUNDFLEX curved formwork was used, which ensured that the circular geometries specified in the architectural plans were accurately replicated. The circular columns associated with the ossuary were constructed using SRS circular formwork.

A significant number of glass blocks were incorporated into the curved reinforced concrete walls. This required a large number of cut-outs and the creation of bespoke formwork inserts. The cut-outs were manufactured and installed by specialists from SH-BAU Mérnöki Kft..

 

 

A 40-centimetre-thick slab above the underground exhibition space

The structural construction of the exhibition space, part of which is situated below ground level, presented a different kind of challenge. Some of the reinforced concrete floor slabs were as thick as 40 centimetres, which placed a significant load of fresh concrete on the formwork and shoring systems.

For the floor slabs, MULTIFLEX floor formwork, GT24 timber trusses and PEP ERGO D-500 floor props were used. For the 40-centimetre-thick slabs, the high load-bearing capacity of the GT24 timber trusses made it possible to optimise the layout of the main beams and the spacing of the supports to suit the specific load requirements. 

During the reinforcement work on the high walls, PERI UP Rosett Flex reinforcement scaffolding was used to provide working platforms. 

In the case of the chapel and the ossuary, in addition to the arched cellar walls, ceiling structures were also constructed that mirrored the arched geometry, which further increased the technical complexity of the construction.

 

 

A unique system followed the tower, which tapered towards the top

One of the most spectacular structural engineering tasks of the project was the construction of the chapel tower, which stands approximately 16 metres tall. On the outer face of the reinforced concrete structure, which tapers towards the top, a DOMINO formwork system was used, whilst the formwork on the inner face was constructed using a traditional timber framework.

Due to the sloping surface, a bespoke climbing system was constructed for the tower using VARIOKIT components. This structure provided a safe working level that advanced continuously upwards in tandem with the construction of the tower, from which both the internal timber framework and the external formwork could be erected.

 

 

Over 5,200 cubic metres of concrete, laid to a precise schedule

The volume of concrete required for the new structures – over 5,200 cubic metres – demanded significant work organisation in its own right. On a project of this scale, the rotation speed of the formwork, the supply of materials, the concreting phases and the formwork removal dates had to be constantly co-ordinated. The quick-to-assemble, heavy-duty systems made it possible to align the successive concreting phases with the contractor’s tight schedule.

 

 

They did not merely supply scaffolding systems

PERI’s role in the project was not limited to supplying formwork and scaffolding materials. PERI engineers drew up detailed formwork and scaffolding plans, carried out the necessary dimensioning, determined the system layouts, and provided ongoing technical support throughout the construction phase. PERI’s responsibilities also included ensuring that the large quantities of formwork materials required for the various work areas and sub-sections were supplied on time and in line with the construction schedule.

Throughout the project, experts from PERI and SH-BAU Mérnöki Kft. worked in close collaboration; rapid decision-making and joint technical problem-solving played a key role in the construction process.

Source: Link

Popular