Final touches: testing underway on the Hungarian section of the Budapest–Belgrade railway line
On the Hungarian section of the Budapest–Belgrade railway line: the switches, buildings, platforms and overhead lines are already in place, and we are now at the stage of conducting power-off operational trials – as reported by Facebook page Zsolt Hegyi, MÁV Group Chief Executive.
He then explained:
This means that even without passengers, but with vehicles, they are testing the track by simulating real traffic situations and checking that everything has been implemented according to plan.
At the control centre built in Kiskunhalas, three specialists manage train traffic from Budapest to the Kelebia border 24 hours a day. From here, they manage and control the switches and signals, monitor the status of the barriers, view camera images of what is happening at the stations, and operate the central passenger information system, explained the head of the state railway company.
Source: Link
-
Current at 2026. 09. 09.
A first-hand look at a career in engineering – Duna Group Szabadegyetem is back
-
Climate-X 2026. 09. 09.
Nyíregyháza Spartacus FC goes green – four hundred solar panels to be installed on the stadium roof
-
Bound track 2026. 09. 15.
Nearly 50,000 people travel on it every day – the refurbishment of the Cegléd main line continues
-
Current at 2026. 09. 09.
Rental flats, Rákosrendező, decentralisation – important ideas were put forward on the Real Estate Beach Conference stage