What is being built?
A modern sports facility may be built at the University of Physical Education
Renovation work can begin on one of the buildings of the Hungarian University of Physical Education and Sport Sciences (MTSE): according to the decision published in the Official Journal of the Public Procurement Authority, the complete modernisation of Building A2 will be carried out by Mozaik Építőipari Kereskedelmi Szolgáltató Kft.. The investment will be realised for a net amount of HUF 293.3 million, and the construction site is located in Budapest's 12th district, at 42–48 Alkotás Street.
Previously, large-scale development took place within the institution; the construction of the university's sports fields and multi-purpose hall was carried out by ZÁÉV Zrt.
Sport and education at university level
The aim of the renovation is to provide the A2 building with a modern, university-standard sports and educational environment. The ground floor will house combat sports areas (judo, karate, wrestling, fencing), while the hall upstairs will be converted for gymnastics. In addition, the changing rooms and the building's mechanical and electrical systems will be completely renovated.
Significant structural and mechanical interventions
Inside the building, unused large-scale water technology and ventilation equipment will be dismantled, and the existing pools will be converted with steel beams and trapezoidal sheet metal roofing, as well as a 20-centimetre-thick monolithic reinforced concrete slab.
A new heating system is being installed: a total of four condensing gas boilers, each with a capacity of 75 kW, with thermo-fan heating on the ground floor and radiant heating on the upper floor. Hot water is supplied by heat accumulators.
Exterior and landscaping work
The investment also includes the renewal of the infrastructure outside the building:
- rebuilt water connection from the street connection,
- improve the sewer,
- replace the ground floor and upper floor doors and windows,
- happens Improving flat roof drainage and insulation,
- They are also tidying up the area around the building, renovating pavements and ensuring accessibility.
The investment in figures
During the renovation of the three-storey building with a floor area of 1,508 m², the following work was carried out, among other things:
- 52 m³ A trapezoidal sheet-reinforced concrete floor structure is being built.,
- 114 linear metres steel beams are installed,
- 670 m² new PVC sports flooring is being installed,
- 77 pieces LED hall lighting fixtures are being installed,
- close 3.5 km an electrical and IT cable network will be built,
- 31 pieces they are replacing the interior door,
- more than 1,800 m² Painting and surface repair is carried out on the surface.
Source: Link
-
Current at 2026. 09. 09.
A first-hand look at a career in engineering – Duna Group Szabadegyetem is back
-
Climate-X 2026. 09. 09.
Nyíregyháza Spartacus FC goes green – four hundred solar panels to be installed on the stadium roof
-
Bound track 2026. 09. 15.
Nearly 50,000 people travel on it every day – the refurbishment of the Cegléd main line continues
-
Current at 2026. 09. 09.
Rental flats, Rákosrendező, decentralisation – important ideas were put forward on the Real Estate Beach Conference stage