Current at
The biggest motorway upgrade in Hungary's history resumes from Monday
Last week, we published our comprehensive material comprehensive material was published, in which we used maps to show where levelling was carried out in 2024 by the engineers, machines and specialists of Hungarian Concession Infrastructure Development Ltd (MKIF Zrt.) in 2024 (the results are particularly impressive, we recommend click here).
The company responsible for a significant portion of the domestic motorway network has now published a announcement on its Facebook page, revealing that the levelling process will resume on 17 March, next Monday.
Information on the progress of these works will also be available on the new, more transparent and searchable interface created on the MKIF website, which can be accessed via this link.
8.7 million square metres of new asphalt paved in two years
The Hungarian motorway operator summarises in its announcement: over the past two years (2023 and 2024), 8.7 million square metres of new asphalt were laid on the roads they maintain. Where necessary, the binder and base layers were also replaced under the top wearing course. During the works, 237 bridges and overpasses were renovated, including the Kőröshegyi valley bridge, as well as a total of 40 rest areas have been renovated.
According to the contract MKIF signed with the Hungarian State, 540 km of the 1,237 km of the expressway network taken over for operation, maintenance and renewal in September 2022 must be brought up to the same technical standard as the rest within three years, by 31 August this year.
The biggest motorway upgrade in Hungary's history will therefore continue this year, following the 15 March holiday weekend, probably from 17 March.
New bridge also under construction
In 2025, an additional 3.2 million square metres of expressways operated by MKIF Zrt. are scheduled to be resurfaced, this includes the main 16%.
In addition, 40 bridges and 30 rest areas will be renovated. Among others, the necessary technical renovation of the Pentele Bridge will continue. Here, the spurs and expansion joints will be replaced,
instead of the old Venice pedestrian and cycle bridge on the M7, a new one will be built.
Most of the work is planned for 2025 on the M3, M7, M1, M35, but there are also 7 other motorways (M15, M85, M86, M30, M4, M70, M8).
At the end of the communication, MKIF stresses that although the resurfacing works will be completed by 31 August this year, the further maintenance and resurfacing of the tracks will not stop. This year's work is intended to ensure the comfort and safety of road users in the future.
Source: Link
-
Road building 2026. 10. 13.
A consortium comprising STRABAG and Duna Aszfalt has been awarded the contract to build the North Macedonian motorway
-
What is being built? 2026. 10. 09.
One of Budapest’s oldest nurseries is being renovated whilst preserving its timber roof structure
-
Current at 2026. 10. 10.
„The focus will not be on Lean’s equipment, but on how we operate” – the ‘Lean in the Construction Industry’ conference in November
-
Bound track 2026. 10. 08.
Déli railway station is set to undergo a major refurbishment, paving the way for double-decker trains
