What is being built?

The special AEROPLEX Közép-Európai Kft. hall at Budapest Airport was built with the help of Hungarian engineering

Published

After the previous Construction Master Award, the Weinberg ’93 Kft. generic construction project has also been awarded the Construction Excellence Award. In the light of this new award, we have investigated what was needed to achieve a project with special parameters and challenges.

The construction of the AEROPLEX Közép-Európai Kft. aircraft hangar was considered a real feat of engineering by the jury that awarded the project the Construction Excellence Award, according to the laudation announced at the Gala on 7 December 2023. The challenges of the ACE (Aeroplex of Central Europe) Hangar, inaugurated at Budapest Airport last March, were explored with the help of the general contractor Weinberg ’93 Kft.. The general designer of the project was ARC-S Group Kft.

Unusual dimensions had to be implemented

AEROPLEX Közép-Európai Kft., based in Sárospatak, was responsible for both the fabrication and construction of the unique steel structure of the new hangar, which was its own investment. The facility, which is considered unique in Hungary, has already earned national attention during its construction, as it was awarded the Construction Master Award at the ÉVOSZ Gala in December 2021.

The size of the hangar made it a special challenge: the span and height were not always a challenge. The hall, which is to be built between two existing hangars and will cover more than 8,200 square metres, had to be constructed with a clear span of 90 metres, a 31-metre high ceiling and a 75-metre wide, undivided door opening on one side. All this made the hangar suitable for the full servicing and maintenance of 31-metre wide-body aircraft.

The unique steel frame structure required for the above was realized by the Weinberg ’93 Kft. production plant in Sárospatak. A customized assembly tool was made for the factory and field assembly, which allowed to significantly reduce the fitting measurements.

On average 40 people worked on the construction

As indicated in our previous article, the assembly was also achieved with special solutions. Among other things, the 90-metre-wide roof main support structure was lifted completely, frame by frame, to a height of 30 metres, on top of the previously erected, rigid pillar frames. This required a strong technical background and the close cooperation of highly qualified and experienced professionals. The erection of the structure involved 5 crane hoists, 3-4 cranes and an average of 40 erectors working simultaneously.

In addition to the above, the praise for the project at the recent ÉVOSZ Construction Excellence Award gala says a lot about the project. "The logistics of transporting your steel structures from Sárospatak to the installation site and the precision with which all the structural elements were put in place was a real engineering feat", reads the citation.

Installation could only start from one direction

Weinberg ’93 Kft. told us that the new building was a challenge because it was built closely between two existing hangars and directly connected to the service building. "We were therefore only able to start the steel structure installation from one direction and, as we progressed, the structure was also used to clad the roof and facade," the report summarised.

In our previous article, we also described how the project involved custom-built material handling systems and alpine engineering. Accordingly, the Weinberg, which has often used innovative solutions in other projects, has already been prepared with great care. "Before the construction work started, the project team was selected in consultation with the company's management so that colleagues with expertise in specialised work would carry out the construction," they told the paper. "The team planned the installation schedule in advance, agreed on the supplies and selected the cranes and lifting equipment needed for the lifting."

Applying the principles of LEAN project management

The Weinberg ’93 Kft. places great emphasis on continuous improvement, and has started to learn the principles of the LEAN and implement them in its construction projects, in addition to its manufacturing processes. The specific requirements of Budapest Airport, as well as the particular environment of the construction site, also provided an opportunity for the project elements to be used in a prominent way. "The airport has special regulations for access and boarding, and the construction site was located in the immediate vicinity of the runway, with limited landfill space available. Precise forward planning was a priority, both in terms of staffing and the continuous supply of materials. It was not possible to improvise on the project."

Sustainability was not left out of this project either

Finally, it was also reported that sustainability, which has always been a key focus for Weinberg ’93 Kft., was also addressed on this construction site. "Glass foam granulate was used to seal the building, packaging materials were collected selectively, and concrete elements covering the area were sent to the airport for recycling."

The Weinberg ’93 Kft. also pointed out that the experience gained in the project will be available at any time at Budapest Airport, which is home to a number of developments.