The renovation of the main railway line in Győr enters its final phase

Published

The last phase will last until 9 December.

Hungary is making steady progress on the renovation of one of the most important railway lines, the main line running from Győr to Vienna, specifically the section between Biatorbágy and Szárliget. several times reported on the work in our newspaper.

The most complex phase of the modernisation will last until 17 November, during which time no trains will run on any of the tracks. The track reconstruction between Szárliget and Biatorbágy is running according to schedule, with the period with the most traffic changes coming to an end: the MÁV staff are already working on the left track. The third and final phase will start on 18 November and the reconstruction will be completed on 9 December.

Major changes expected on Saturday

Accordingly, from 18 November, partial traffic on the rebuilt left-hand track of main line 1 will be reopened, and the normal traffic regime will be restored on line 5, which has been temporarily used for freight trains only in recent weeks. From today, passenger trains will also be running again between Székesfehérvár and Komárom.

The construction will be carried out by MÁV Zrt."s subsidiary, MÁV FKG, with HUF 32.5 billion allocated for maintenance.

Detailed information important for travellers is available on the mav.hu/egyesvonal website, but of particular interest is the news that from 18 November, international trains and certain morning rush hour, afternoon and evening passenger trains and G10 services will once again run their full routes to and from Budapest. to and from Budapest.

These works were carried out in the first two phases

The communication also details the full renovation process. During the first phase of the work, which is divided into three phases and will last around three months, the rails and concrete sleepers on the left-hand track were replaced and the ballast was laid.

On average, two thousand metres of track had to be ballasted and one thousand five hundred metres of track rebuilt every day.

The simultaneous renewal of the two tracks between Szárliget and Biatorbágy has been on schedule for the last two weeks with the ballast machines, the track-laying machine chain and the machines and trains involved in the works and transport. In the second phase, which is currently coming to an end, the substructure (embankment, notch) of the two pairs of tracks will also be restored over a total length of two and a half kilometres, i.e. a soil stabilising and waterproofing layer will be created under the track in these sections, and the track will be completely rebuilt.

Several stops to be renewed

During the entire closure period, MÁV will also carry out other maintenance work at Biatorbágy, Herceghalm, Bicske and Szár stations to improve passenger comfort.The most visible element of this is the renewal of the platforms, with about 150-200 metres of new asphalt pavement being laid at these locations. In addition, the façades of the station buildings will be repaired and painted, as well as the walls of the waiting rooms, toilets and underpasses, and the rain shelters and benches will be cleaned and repaired (one of the platforms in Biatorbágy will be renewed next spring).

During the third phase, MÁV FKG will carry out the reconstruction of the right track, similar to the reconstruction of the other track during the first phase.

More than 1,100 workers and experts from MÁV and its subsidiary MÁV FKG are involved in the design and construction processes to complete the track reconstruction in the shortest possible time, before the colder winter weather, and by the deadline of 9 December.

Source : Link