The new railway bridge over the Szerém road will soon be in place
The new railway bridge over Szerémi Road and tram line 1 is being assembled on site from elements weighing 10-17 tonnes each. Following precise alignment, welding and corrosion protection work, the structure, weighing a total of nearly 250 tonnes, will be pushed into place by specialists, according to a statement by Építési és Közlekedési Minisztérium.
The special technology allows the bridge structure to be put in place in one piece, without major disruption to road and tram traffic, and without the need to stop traffic during the installation.
For the operation, the specialists will construct temporary intermediate supports at only one point, and the bridge will be placed on the sliding deck, with the help of the permanent and temporary supports for the pushing. In order to minimise the enormous forces on the structure and to ensure the necessary stability of the operation, the bridge is pushed using a so-called "assembly tube", which is a temporary extension of the bridge structure by means of a light steel structure. The bridge itself is pushed using hydraulic pushing equipment
- you have been informed.
Track extension, new stops, green corridor: this is how the Southern Circular Railway is transforming the capital
We regularly report on the Southern Circular Railway project, which, as stated in the ministry's announcement, is one of the most important investments in terms of transport in the capital and the country, but its significance goes beyond that.
A complex, 21st century urban development project to renovate and extend the rail link between Ferencváros and Kelenföld railway stations and to create a major green corridor from the Danube to the Buda Hills.
Three European Union railway corridors affecting Hungary also pass through this route. As a result of the project, two new railway stations will be built in the Közvágóhíd and Nádorkert areas, and railway capacity will be significantly expanded. The creation of three or four tracks instead of two and the construction of new stops will dramatically increase the capacity of suburban and urban railways, while the green spaces created will improve air quality. The construction will be carried out by V-Híd Zrt., and the implementation design will be carried out by Kontúr Csoport Kft..
Source: Link
-
Bound track 2026. 10. 07.
Aurora beneath the Apennines – Another tunnel is being built on the Naples–Bari railway line
-
Road building 2026. 10. 13.
A consortium comprising STRABAG and Duna Aszfalt has been awarded the contract to build the North Macedonian motorway
-
What is being built? 2026. 10. 09.
One of Budapest’s oldest nurseries is being renovated whilst preserving its timber roof structure
-
Current at 2026. 10. 10.
„The focus will not be on Lean’s equipment, but on how we operate” – the ‘Lean in the Construction Industry’ conference in November