What is being built?
From a cultural centre to an experience centre - a new function for the Dimitrov Cultural Centre in Veszprém
More than fifty years ago, in 1973, the House of Culture of Veszprém County was inaugurated, taking the name of "the great son of the Bulgarian people", Georgi Dimitrov. The late-modern, hexagonal main building and its attached annex, a simple log structure with ribbon windows, were once a hive of activity. The community centre stood empty for a good ten years, and the condition of the lobby, highlighted by an exciting split curtain wall, has deteriorated badly in recent years. Finally, in connection with the European Capital of Culture events in Veszprém, a renovation was found, and it was indeed timely.
During the programme series, the renovated, smaller wing of the former cultural centre was handed over, which quickly found new residents. Musicians and visual artists were given space in the 1,100-square-metre building. As the programme organisers wrote:
"The Dimitrov project brings together everything that is important to us at the EFC: renovating an old, disused building and bringing it to life, counting on the activity of the local population and artists. We have envisioned a community and creative space where people from different artistic disciplines can create, work and stimulate each other."
They found a place here:
- for musical productions (rehearsal spaces and recording studios),
- for artists, photographers, filmmakers, visual artists (creative workshops),
- the Hangar Light Music Centre, which provides complex music training, and
- community spaces.
CODE
However, the renovation of the main building is still ongoing. Commissioned by the Local Government of Veszprém County, the first part of the renovation, carried out by VEMÉV-SZER Kft. and its partners, the external work has already been completed and the scaffolding has been removed, revealing sculptor László Marosán's sculpture in the Culture Square and the curtain wall.
The interior is currently being worked on and will house the Digital Experience Centre (Center of Digital Experiences – CODE). According to the presentation on the VEB2023 website, the transformation will be followed by an Exhibition Space on the ground floor of the building, where visitors will be able to see permanent and temporary digital installations. The Hexagon, a former theatre space on the first floor of around 400 square metres, will be used as a 360-degree projection space for 360-degree projection screenings, including theatre and music events. The stage and backstage area will be transformed into a studio for 180-degree interactive and three-dimensional projections, as well as projection-accompanied performances.
The renovation of the main building is progressing well
Commissioned by the Local Government of Veszprém County, VEMÉV-SZER Kft. and its partner company, Mintech Kft. As we learned from Ilona Grószné Hellebrandt, the facility manager of VEMÉV-SZER Kft., in addition to the aforementioned works, the building with a floor area of approximately 2300 m2
- a new ventilation and cooling/heating system, and
- they also carry out repairs and flushing of the old system.
- The replacement of the ground floor windows and doors will start soon and
- the installation of interior cladding,
- the covering of the radiators,
- the design of stair rails, and
- the construction of furniture and counters on the ground floor, and
- the design of low-current systems.
The production design of the interior elements is currently underway. In parallel with the interior works, the paving of the paved area in front of the building will soon be started: the landscaping and planting around the building will bring it back into the urban fabric. This will allow the long-abandoned building to become an integral part of the city again.
Source : Link
-
Road building 2026. 10. 13.
A consortium comprising STRABAG and Duna Aszfalt has been awarded the contract to build the North Macedonian motorway
-
What is being built? 2026. 10. 09.
One of Budapest’s oldest nurseries is being renovated whilst preserving its timber roof structure
-
Current at 2026. 10. 10.
„The focus will not be on Lean’s equipment, but on how we operate” – the ‘Lean in the Construction Industry’ conference in November
-
Current at 2026. 10. 13.
It’s time to provide information to those in the sector – that’s what this year’s Építőipar Summit was all about