What is being built?

Paks II: the elements of the zone melt trap that arrived on the Danube were lifted ashore in two days

Published

In two days of coordinated and precise work, the elements of the zone melt trap were dredged in the cold water channel of the Paks Nuclear Power Plant.

The components of the zone melt trap, each of which is enormous in size, are now lined up at the construction and installation base, according to a recently published information sheet published on its website Paks II Zrt. (we reported on the arrival of this giant structure in our newspaper here). This is the largest piece of equipment at the new nuclear power plant, weighing more than 700 tonnes. It was lifted from the cargo ship that brought it to the Paks Nuclear Power Plant's cold water channel using a heavy-duty crane.

Photos: paks2.hu

"We have arrived at the most spectacular stage of the Paks II project so far, the lifting of the zone melt trap that will ensure the safety of the plant. It has been an extremely intense, industry collaborative effort over the past few days"

- said the programme director of Paks II. Zrt..

Gábor Kiss László said that the coordinated work of the company in charge of the construction of the new nuclear power plant, the main contractor ASE JSC, the MVM Paksi Atomerőmű Zrt., the MVM Ovit Zrt. and the Austrian Danube Shipping Management Service GmbH resulted in the removal of all the elements and their transfer to their temporary location in two days.

July 2020 marked the beginning of the zonal trap story

The final location of the zone melt trap will be under the reactor vessel, where it will it will perform a safety function. Safety was also the focus during transport and lifting, emphasised the programme director.

The story of the zone melt trap began in July 2020 with the nuclear certification of the manufacturing company Energotex. Extensive technical documentation was prepared and then production started, which was monitored by the Paks II. Zrt. specialists and representatives of the National Nuclear Energy Office. The nuclear authority also supervised on site the dismantling of the batteries and their transport to the site.

Unit 5's zone melt trap is the first long production run equipment to be completed and arrive in Paks.