Road building

Renovation of the exploratory road of the Industrial Park in Balassagyarmat completed ahead of schedule

Published

During construction, HE-DO had to ensure continuous access to all nearby industrial facilities.

The specialists at HE-DO csoport completed the renovation of the access road to the Balassagyarmat Industrial Park ahead of schedule. As part of the project, approximately 3.5 hectares of land were also connected to public utilities, according to the company's website.

The construction company won the public procurement tendered by the local authority on its own. HE-DO took over the worksite in January 2023 and completed the works in July.

"According to the contract, we were supposed to finish the work by 26 August, but we delivered the road more than two weeks earlier, on 10 August. Because of the heavy rainfall, the weather was not kind to us, so we were prepared for possible soaking and as a result we were not late in completing the project"

- said Gábor Pintér, chief architect of HE-DO.

The works were needed mainly because the asphalt pavement was ageing and deteriorating, and the section was not wide enough for the heavy traffic.

The timing of the works required a high level of coordination

"At the beginning of the project, we demolished the fence and a small building, and then prepared the area for paving. Then, to protect pedestrians, we constructed the sidewalk, storm sewer, missing water and electrical mains, and widened the trail structure."

- said the Chief Architect.

Later, the specialists created a sunken kerb with a pavement drain on both sides of the road, and finally, they laid two layers of asphalt. A particular challenge for the construction company was that it could only work with a half-lane road closure.

"We had to ensure the uninterrupted flow of traffic to all the nearby industrial facilities, including the buses transporting workers. When we were laying the wearing course in front of the entrance, we made arrangements with the industrial park's suppliers to schedule the arrival later, as the surface needed a few hours to cool down" - recalled Gábor Pintér.