Development of the road between Kecskemét and Nagykőrös is in full swing

Published

Colas is working on the project, which will cover around 10 kilometres and will involve the four-laning of almost 3 kilometres of the main road.

In February 2022, the implementation of the 441 road project began. In this investment project covering approximately 10 kilometres, a significant section of the 441 main road in Kecskemét will be expanded to four lanes, while the existing 2×1 lane pavement will be reinforced over a 7.29-kilometre stretch between the 445th Kecskemét northern bypass and Téglagyári Street in Nagykőrös.

One of the reasons for the investment is the significant increase in the number of commuters between Kecskemét and Nagykőrös in recent years due to the major investments in Kecskemét, which has led to the deterioration of the main road. As a result of the improvement, the inhabitants of the settlements in the area can reach their destinations faster and safer.

The project, worth a net HUF 8.495 billion, is being implemented under the Regional Road Investment Programme (TKB) from domestic sources, with construction being carried out by Colas Út Zrt..

As the successor of NIF Zrt., Építési és Közlekedési Minisztérium, as the investor, issued a statement on the current status of the works on 1 September.

Construction work on the roundabout will start soon

Works have begun on the reconstruction of the Nagykőrös Kálvin tér junction into a roundabout junction, which will be implemented in several construction phases with temporary traffic diversion. The replacement of underground utility lines is currently underway. After the utilities are rebuilt, road works will start in the second half of September.

The construction of temporary diversion roads and service roads on the 441 main road in the Pest County suburban section is completed. Construction works on the main carriageway started at the end of August 2023 and are expected to last until December 2023. During the construction period, a temporary 2×1 lane diversion road will be available. At the same time, the construction of service and cycle lanes is underway on the already completed section of the main suburban road.

Continuous traffic restrictions are expected until the end of construction

The construction works of the storm sewer and the construction of street lighting were completed on the section of Kecskemét Katonateleppi on the Mathiász Elementary School side. At the same time, other utility works were completed on the site concerned. Work on the military section is expected to continue until the project is completed. The construction of the traffic light intersections is underway, as well as the construction of the affected sections of Vineyard and Sunshine Streets.

Platán Street and Zsigmond Katona Street have been unidirectional on the section between Lombos Street and Zsigmond Ferenc Street in the direction of Zsigmond Ferenc Street, as road construction and water works have started in the two connecting streets; this will affect road and partially pedestrian traffic. The restrictions are expected to last until the end of September/October 2023.

Construction of the service road on the section of the main road 441 between Nagykőrös and Kecskemét has started, the section of Naspolya street between Katona Zsigmond street and the main road 441 has been closed due to the progress of the works. As a result, the possibility to drive onto the main road 441 from Naspolya Street has been eliminated, and during the works, residents will be able to drive onto the main road 441 from Gyökér Street.

The project is expected to be completed in Q3 2024.