Bátonyterenye bypass to be completed soon

Published

Complex investment on the main road 23 in Vághajra

In September 2022, the foundation stone was laid for the bypass road between Bátonyterenye and Kisterenye on Main Road 23. A complex investment is therefore being built in the Bátonyterenye area on behalf of Építési és Közlekedési Minisztérium, which is being carried out by Colas Út Zrt. and HE-DO.

Thanks to the work of Colas and HE-DO, the crossing section of the main road will be free of transit traffic and the connection between the districts of Nagybátony and Kisterenye will be established.

Roundabouts and car parks to be rebuilt

A 2 x 1 lane bypass road was built, 2.3 kilometres long, ensuring the bypass of the main road 23 in the inner area, as well as a 2.19 kilometre long north-south road connecting two parts of the municipality, Kistenyeré and Nagybátony. The investment will include the construction of associated roundabouts, parking lanes and bus shelters, as well as the renovation of level crossings, bridges and cycle paths in the area. Street lighting, planting, water engineering, environmental protection and traffic engineering works will also be carried out.

In early June, work began on the new BM-043 bridge structure on the new road linking Route 23 to the Kazar Creek.

On section HE-DO, nearly 11 000 m² of AC-11mF wearing course was installed in the first week of June, and the painting of the final pavement signs and the installation of road signs started on the completed wearing course.

An important part of the construction of the bypass of road 23 has also been completed: with the construction of a 200-metre section of the K1.1 cycle path, the Zagyvavölgy cycle path was connected to the cycle path to Erzsébet utca in Kisterenyei.