Road building

A new era of cycling in Tarnaok could begin

Published

Photos by Mihály Erdei/magyarepitok.hu
A newly built cycle path in a Pest county town will make cycling safer. The development is being carried out by SWIETELSKY Magyarország Kft..

On behalf of the Local Council of Tárnok, the SWIETELSKY Magyarország Kft. cycle path development project is being implemented in the municipality. Construction manager Gábor Pethő provided our newspaper with details of the implementation.

As an introduction, the expert said that the aim of the project is to create safe and sustainable transport options, as there were no cycle paths in Tárnok, and the increased motor traffic has made cycling difficult.

Photos by Mihály Erdei/magyarepitok.hu

One section already completed

The project consists of three phases, two of which will be carried out by SWIETELSKY. For both phases, works started in early November, following contracting and short preparation periods in mid to late October 2024.

"The Szőlőhegyi Street part of the project will be completed by the beginning of February 2025, except for the pavement markings. Depending on the weather, the earliest we could replace them was mid-March. I would particularly like to highlight the positive attitude of the client and the engineer in allowing these works to be carried out only at the appropriate time"

- we were informed by the site manager.

The technical hand-over of the Szőlőhegyi road cycle lane was successfully completed on 19 March 2025, and since then cyclists have taken possession of it. The opening of the Berki út section is scheduled for the end of April 2025.

Main technical details:

  • Vineyard Street section: A two-way, directional cycle lane has been built for 250 metres. With the widening of the asphalt road, the total width of the road was increased to 8.5 metres, of which 1.5-1.5 metres is the cycle lane and 5.5 metres is for two-way traffic. As part of the improvement, 250 metres of drinking water mains were replaced and 220 metres of storm water drainage was installed.
  • Berki Road section: A two-way cycle path with a pavement width of 2.55-3.00 metres will be built on 750 metres of completely new track. 580 metres of stormwater drainage will be constructed, 160 metres of closed pipe sections with manholes and gullies will be installed and a safe crossing will be provided on the Sóskút road.

For both sections, the project also includes the installation of final traffic engineering elements such as barriers, pavement markings and signs.

During the construction, the experts faced several challenges

The construction manager explained that the cold, rainy and snowy weather and unexpected utility situations made the construction difficult and challenged the experts. In addition, the works had to take into account future development plans, such as the future construction of bus stops and pedestrian crossings and their possible connections.

"I am grateful to my well-trained colleagues and to our reliable suppliers and subcontractors for the quality work we managed to deliver on time despite the weather conditions"

- said the expert.

Two-way traffic was maintained throughout the work, apart from occasional side street closures and half-lane diversions.

The development will not only make transport safer for locals, but will also create opportunities for the settlement to connect to the surrounding cycling networks, such as the Budapest-Balaton cycle route. The new infrastructure will thus make it easier for cyclists not only to get to work, but also to access services, shops and leisure facilities.

Source : Link

Popular