Strategic gas storage works in a highly dangerous environment
As the only gas storage facility in Transdanubia, the Pusztaderics gas storage facility plays a key role. We obtained information about the maintenance work currently underway there from the contractor Vabeko Kft..
Capacity more than tripled from an initial 100 million cubic metres
According to a report from a leading company in the Hungarian gas industry, the Pusztaederics Underground Gas Storage Facility in Zala County was the first natural gas storage facility in Hungary, established in 1979.
"The underground gas storage facilities essentially use the remaining porous layers of the depleted underground gas fields to store natural gas, which helps to serve seasonal heating needs and ensure a steady supply to the national high-pressure transmission system," the summary reads. Accordingly, the storage facility in question became available for this purpose following the extraction of the natural gas from the Hahot-Ederich natural gas field between 1951 and 1972.
With an initial capacity of 100 million cubic metres of mobile gas, the storage capacity, the number of wells and the capacity of the surface technology were further increased in 1988 and 1991. Currently, the nominal mobile gas capacity is 340 million cubic metres and the cushion gas capacity to ensure the smooth operation of the storage is 266 million cubic metres. "The cushion gas is the gas reserve that is responsible for the stability of the storage layer and is always present in the layer during the operation of the storage facility. The mobile gas reserve is the quantity of gas that can be withdrawn or injected per cycle, i.e. the commercial gas reserve," the statement explained.
These two processes determine the operation of the repository
Another important piece of basic information in the technical material provided to us is that gas storage facilities have two modes of operation.
<During storage, which typically takes place in the summer, gas from abroad and from domestic production is injected into the storage layers via compressors and production injection wells. In contrast, the storage process is usually associated with the heating season, when the gas injected during storage is extracted from the storage layers, also through the production injection wells.
During storage, the stored pipeline natural gas in the storage layer becomes enriched with water, solids (the rock material of the storage layer) and other hydrocarbons, which requires purification and conditioning before it is injected into the pipeline. The maximum daily storage and withdrawal capacity at the pusztadericsi complex is 2.9 million cubic metres.
They also mentioned that the owner and operator of the facility is Magyar Földgáztároló Zrt (Hungarian Natural Gas Storage Ltd.), which is a member of MVM Csoport. The Pusztaederics Underground Gas Storage Facility is the only natural gas storage facility in Transdanubia, therefore it plays an extremely important role in maintaining the hydraulic balance in the western part of the national high-pressure transmission system.
The Vabeko has permanent staff in all storage facilities
In the summary, it is stressed that the machinery and equipment that operate the facility operate in accordance with strict regulatory and operator requirements, and therefore continuous maintenance and improvement work is needed to ensure its safe operation. In 2011, Vabeko Kft. started to maintain the four domestic commercial storage facilities (Hajdúszoboszló, Zsana, Kardoskút and Pusztaederics). "As a result, we have permanent staff at all storage facilities to carry out day-to-day operations," they say. "In case of need, i.e. in the case of larger-scale construction activities, we will dispatch manpower and equipment from our central staff to the site in the quantity and quality required for the task."
It was pointed out that the activity required to maintain the facility is generally not project work, but ongoing maintenance or a series of maintenance and development tasks.
"The last major upgrade was about ten years ago. This was the completion of a project to extend the life of the storage facility to ensure its future smooth operation. At the same time, specific improvements to the technological parts have been ongoing since then, aimed primarily at increasing technological safety, energy efficiency and operational flexibility, as well as improving the quality of the natural gas released."
Most tasks are performed with continuous gas concentration measurement
Much of the work in question must be carried out on site in a highly hazardous environment: high pressure, flammable and explosive atmospheres, hazardous substances and other factors. "We work on the basis of daily work permits, both for local staff and for workers temporarily delegated to the task. The equipment, machinery and tools used are certified and most tasks are carried out with continuous gas concentration measurements."
At the end of the report, the repository is currently running several tasks simultaneously under the implementation of Vabeko. Among others, there are
- inspection of the heat exchangers of a gas preparation plant,
- Replacement of two boilers in the heating plant,
- replacement of the main shut-off fittings of the gas preparation equipment with a bypass branch,
- maintenance of the gas metering equipment and metering sections,
- and annual maintenance of glycol regeneration equipment.
Source : Link
-
Road building 2026. 10. 13.
A consortium comprising STRABAG and Duna Aszfalt has been awarded the contract to build the North Macedonian motorway
-
What is being built? 2026. 10. 09.
One of Budapest’s oldest nurseries is being renovated whilst preserving its timber roof structure
-
Current at 2026. 10. 10.
„The focus will not be on Lean’s equipment, but on how we operate” – the ‘Lean in the Construction Industry’ conference in November
-
Bound track 2026. 10. 08.
Déli railway station is set to undergo a major refurbishment, paving the way for double-decker trains