Bound track
Rehabilitation of the railway track at Kétpo to be completed soon
On 9 July 2023, a freight train travelling from Szolnok Békéscsaba−Lőkösháza derailed between Tiszatenyő and Mezőtúr stations at the Kétpó traffic junction. Nine of the seventeen carriages derailed, while eight carriages and the locomotive remained on the tracks.
For almost three weeks, experts have been working on the busy railway line to repair the damaged rails, safety equipment and overhead wires. The accident damaged both tracks and trains were unable to run on this section for days. Traffic on the left track was able to resume after the technical rescue, but delays and cancellations are still expected.
According to experts, the derailed carriages caused damage that could take weeks to repair. The repair work was assisted by the V-Híd Zrt. SMD-80 track-laying machine, which was transferred from the construction of the Budapest−Belgrade railway line.
István Sárváry, the general manager of V-Híd Zrt., said that the SMD-80 is rebuilding hundreds of metres of damaged railway track at Kétpo. With the reallocation of the machine, the work can be completed much earlier than planned.
When the track is completed, the timetable will be restored within a short time, so passenger and freight trains will be able to run as usual.
Source : Link
-
Road building 2026. 10. 13.
A consortium comprising STRABAG and Duna Aszfalt has been awarded the contract to build the North Macedonian motorway
-
What is being built? 2026. 10. 09.
One of Budapest’s oldest nurseries is being renovated whilst preserving its timber roof structure
-
Current at 2026. 10. 10.
„The focus will not be on Lean’s equipment, but on how we operate” – the ‘Lean in the Construction Industry’ conference in November
-
Current at 2026. 10. 13.
It’s time to provide information to those in the sector – that’s what this year’s Építőipar Summit was all about