What is being built?
WHB wins significant work in CATL's giant investment in Debrecen
WEST HUNGÁRIA BAU Kft. has won a large-scale project at the Contemporary Amperex Technologies Limited (CATL) giant complex in Debrecen, according to information sent to our newspaper by the company. The Hungarian company will carry out the structural construction of one half of the Chinese company's central production hall (PC Package 2) and the associated ancillary building.
A total of 110 thousand square metres of hall space is being built
CATL - the world's largest battery company - is making the largest ever investment in Hungary in Debrecen, worth around HUF 3000 billion. The company has a significant international market share of over 30 percent. Well-known car manufacturers such as BMW, Ford, Tesla and Volkswagen use CATL batteries in their products.
As part of the giant project in Debrecen, WHB will carry out the construction of a total of 110,000 square metres of hall space, which will be completed:
- excavation of monolithic reinforced concrete headstocks,
- the construction of monolithic headstocks,
- the placement of precast reinforced concrete elements,
- and the installation of the steel reinforcement.
The WHB has already started work on the Debrecen production hall, including earthworks and the tasks mentioned above.
An inspiring example for other Hungarian companies
In the WHB report, it was stressed that such significant investments can contribute to the development of the Hungarian economy and create opportunities for Hungarian construction companies to demonstrate their knowledge and skills on an international level. "The participation of WHB in the CATL investment in Debrecen can serve as an incentive for other Hungarian companies to undertake projects of similar size and importance and strengthen Hungary's position in the industry", the report said.
The company is focusing on several factors in the investment. The first of these is scalability: the project requires a high level of flexibility due to its size alone, and in this respect the WHB adapts to the scale and complexity of the investment, with the necessary resources and skilled workforce.
Large-scale projects typically have strict deadlines, so WHB also plans carefully to ensure that all work is completed on time and the project can proceed according to schedule. Meeting stringent quality standards is also a top priority. The CATL has high expectations for the quality of the investment, and for the WHB, high quality workmanship is also critical.
They also find common ground between different cultures
All this implies a high level of logistical organisation: a huge investment requires extensive logistical and infrastructure plans. The WHB will ensure that materials and equipment can arrive at the job site smoothly.
In such large-scale projects, workplace safety and security are also of paramount importance. The company adheres to strict standards to maintain health and safety to avoid workplace accidents and potential environmental pollution.
In addition, it was also stressed that, as such a development involves a significant number of participants and subcontractors, effective communication and cooperation between all parties is also key to its successful implementation. The Hungarian firm also welcomes the challenges that intercultural communication presents: being involved in an international project with teams from different countries, understanding differences and ensuring that they work in harmony is critical to successful project management.
These departments should work together
As several departments of WHB are involved in the development, the effective management of inter-company communication is also key to the task. The summary also detailed which departments need to work closely together:
- A Enterprise Department carried out the preparation of the project, in coordination and agreement with the implementation. However, their work does not end here: they will continue to be the backstopping actors in the CATL construction, supporting the project. In addition, based on feedback, the implementation will support the department in preparing for further tenders and winning new investments.
- A project management team is responsible for organising all activities, meeting deadlines and using resources efficiently.
- A engineering department plans and carries out the various building and construction tasks, and supervises the work and its quality.
- As a member of the WHB Group, the TSPC Design Office has also played a major role in the project, providing design coordination and expertise in architectural, engineering and BIM-based design and construction, bringing their knowledge and experience to bear to ensure a high quality implementation.
- A finance department provides the necessary funding and cost planning, while the Purchasing department arrange the purchase of materials and equipment for the project.
- A human resources department is responsible for recruiting the right professionals and ensuring the right skills are available.
Sustainability and innovation go hand in hand
It was also stressed that projects of this size offer the opportunity to introduce innovative solutions and to consider sustainability aspects together."WHB has the potential to apply new technologies during construction and to find solutions that reduce the ecological footprint".
The report concluded by pointing out that the construction process will be complex, but the success of the project will be guaranteed by the experience, expertise and competence of the Hungarian company, which has previously worked on the Debrecen project of the Chinese Semcorp company and other foreign projects."Such mega investments offer significant challenges, but also exciting opportunities. WHB will carry out the contracted work with the right expertise, planning and cooperation, contributing to the successful implementation of the CATL production hall in Debrecen."
Source : Link
-
Road building 2026. 10. 13.
A consortium comprising STRABAG and Duna Aszfalt has been awarded the contract to build the North Macedonian motorway
-
What is being built? 2026. 10. 09.
One of Budapest’s oldest nurseries is being renovated whilst preserving its timber roof structure
-
Current at 2026. 10. 10.
„The focus will not be on Lean’s equipment, but on how we operate” – the ‘Lean in the Construction Industry’ conference in November
-
Current at 2026. 10. 13.
It’s time to provide information to those in the sector – that’s what this year’s Építőipar Summit was all about