Győr reclaims its iconic building as an innovation centre
The Science and Innovation Park of Széchenyi István University was inaugurated in Győr on 7 November. The complex, rebuilt from the former iconic building of the Kocka biscuit factory in Győr, was built by a consortium of WEST HUNGÁRIA BAU Kft. and EURO GENERÁL Zrt..
In the development, which began in January 2022, only the floor panels, pillars and floor beams remained from the old facility. We previously reported on the interesting aspects and challenges of the project in this article. During the conversion of the former industrial monument, the demolished facade elements were also recycled. However, the concrete elements of the façade could only be demolished by installing steel reinforcements in parallel, as the remaining structure was not structurally stable on its own.
Creative industries and start-ups will also have space in the new building
The project included the construction of a curtain-like steel mesh around the building on four sides as a visual feature, and a service corridor with an exit. The spaces created in the building have the following functions:
- multifunctional presentation, service and community spaces on the ground floor of the centre;
- the flexibly variable intermediate levels were created as "creative industry" spaces;
- an innovation layer for start-up type activities was built;
- and three floors for educational purposes;
- and on the top floor, the project office of the TIP (Territorial Innovation Platform) with external terraces.
Two more phases of investment
Speaking at the event on Tuesday, János Csák, Minister of Culture and Innovation, said that the government's goal is for Hungary to be in the top ten of the world's 200 countries in terms of innovation by 2040. To this end, the minister said, the government spends around 300 billion forints annually on innovation, with the amount amount amounting to 2,100 billion forints in the last seven years.
Róbert Balázs Simon, Fidesz Member of Parliament for the region, explained that the renewal of the former Győr Biscuit and Wafer Factory's cube building was the first stage of the Science and Innovation Park. The second phase will be completed in 2025 and the third phase in 2030, with the development of the area next to the building.
Csaba András Dézsi, Mayor of Győr (Fidesz-KDNP), said that as the university or Audi Hungaria develops, so does the city. Bálint Filep, President of the Széchenyi István University (SZIE), added that the building could become an important economic location.
SZIE and Audi agree on strategic cooperation
Tamás Kolosvári, Head of the Innovation Centre, said that the first phase of the Innovation Park was completed with HUF 6.8 billion from the Economic Development and Innovation Operational Programme. Alfons Dintner, chairman of the board of Audi Hungaria Zrt., said that the relationship between the university and Audi had been fruitful so far, and the innovation park would take the company's next level strategy to an even higher level.
At the end of the handover ceremony, Széchenyi István University and Audi Hungaria Zrt. signed a strategic cooperation agreement, taking a 30-year cooperation to a new level. The agreement covers, among other things, the practice-oriented development of training courses, the organisation of pre-recruitment and industrial internship programmes, as well as joint research, development and innovation projects related to sustainability.
Source : Link
-
Road building 2026. 10. 13.
A consortium comprising STRABAG and Duna Aszfalt has been awarded the contract to build the North Macedonian motorway
-
What is being built? 2026. 10. 09.
One of Budapest’s oldest nurseries is being renovated whilst preserving its timber roof structure
-
Current at 2026. 10. 10.
„The focus will not be on Lean’s equipment, but on how we operate” – the ‘Lean in the Construction Industry’ conference in November
-
Bound track 2026. 10. 08.
Déli railway station is set to undergo a major refurbishment, paving the way for double-decker trains