What is being built?
17 thousand square metres of reinforced concrete structure built in three months with Leier products
The Leier Hungária Kft. is building the new 17,000 m² industrial area in Pápa in cooperation with Merkbau Zrt., is constructing a new 17,000 m² building complex in the industrial area of Pápa. During the investment, the production hall, warehouse and office building intended for lease were constructed simultaneously, in one phase, at record speed.
Our newspaper Gábor Takács, the business unit manager of Leier precast reinforced concrete structures, informed us about the development. He revealed that the entire reinforced concrete structure of the building complex for one of the world's leading automotive suppliers was completed in 3.5 months, with
- 123 spouts and the same number of pillars,
- 220 soft iron beams and tensioned main beams in total,
- nearly 8.000 m2 bark wall,
- 6.000 m2 circular cavity slab,
- two staircases and
- four truck docks have been installed.
Thus, the entire reinforced concrete structure of the building could be realised with the Leier's own elements.
Of course, the company also used a wide range of its products: manhole elements, paving stones and retaining wall elements for drainage and road construction were also supplied from Leier's own factory.
New technology, unusual schedule
Gergő Bőti, the project manager of the Merkbau Építőipari és Kereskedelmi Zrt. also gave us an insight into the details of the construction of the hall. As we found out, here the precast reinforced concrete bark walls were placed between the columns, which determined the sequence of construction of the building, generating a fragile schedule. After the pillars were erected, the walls were installed, and only then could the roof beams, main beams and edge beams be put in place. This reversed the sequence of the roof trusses, the trapezoidal sheeting and the roof deck,
The walls were completed before the roof structure.
The complex schedule required a complicated production sequence and coordinated deliveries, which had to be coordinated from several factories of the manufacturer. The prefabricated structure was already on schedule, and the production and delivery of the elements went smoothly, in line with the construction schedule.
In addition to their technical performance, the prefabricated frame elements and the bark wall and slab elements are also of an outstanding visual quality.
This was also helped by the advantage of prefabricated structures, where the opening sizes were known at an early stage and the manufacturer designed them precisely according to the production plans. This meant that orders for doors, windows and gates could be placed at an early stage of construction, virtually eliminating the survey phase of the opening process and saving considerable time during construction.
New hall to be completed in less than 12 months
The record-breaking construction time was made possible by the pre-stressed hollow core slabs, which are currently the most economical slab system available, emphasised Gábor Takács. The Leier hollow slab beams (LÜF) are prefabricated reinforced concrete prestressed slab elements that are also suitable for covering larger spaces. By placing the floor slabs side by side, a load-bearing floor structure can be created that does not require on-site support, formwork or reinforced concrete fields; it can be loaded immediately after installation.
The project was particularly challenging due to the increased groundwater levels caused by the June rains, but the rapid construction technology also reduced the time needed for the drainage works.
As for the current progress of the project, we learned that all the reinforced concrete frame elements and the reinforced concrete structure of the office section have been completed, and the trapezoidal slab hall roofing is currently under construction. The project manager stressed that thanks to the prefabrication technology, the interior works could start in the autumn, as only minimal formwork work was needed.
The construction, which started at the end of June 2023, is scheduled to be completed in less than 12 months by the Leier group, with the turnkey handover of the entire building expected in summer 2024.
Source : Link
-
Bound track 2026. 10. 07.
Aurora beneath the Apennines – Another tunnel is being built on the Naples–Bari railway line
-
Road building 2026. 10. 13.
A consortium comprising STRABAG and Duna Aszfalt has been awarded the contract to build the North Macedonian motorway
-
Current at 2026. 10. 05.
Sofitel Hotel is the only Hungarian project in the running for the Dalux Award 2026 award – Watch the video too!
-
What is being built? 2026. 10. 09.
One of Budapest’s oldest nurseries is being renovated whilst preserving its timber roof structure