What is being built?

Another VELUX investment by WHB in Fertőd

Published

The redevelopment of the L5 hall has already begun, but we also report on the progress of the two other developments.

VELUX Magyarország Kft. has received another order from WEST HUNGÁRIA BAU Kft. This leading Hungarian construction company is carrying out the reconstruction of the 26-year-old L5 building and its conversion to suit its new function, as well as connecting the P3 production hall to a new building section in Fertőd.

As previously mentioned, VELUX Magyarország Kft., a manufacturer of roof windows, is collaborating with WHB on several projects: the latter company is responsible for the general construction work on the VELUX L5B hall in Fertőd and the VELUX GP4 hall in Fertőszentmiklós.

A new connecting building will also be built

The reconstruction and functional change of the building marked L5 is described in WHB Facebook page, this was justified by internal production planning, similar to the other two projects, as part of a longer-term process. The project includes the construction of a new connecting building, the complete dismantling of the mechanical and electrical systems in the building to be converted, and then its complete reconstruction.

In addition to this, WHB will also carry out the demolition and construction of the shell and side wall, the reinforcement of the supporting structure, and reinforced concrete and steel structural work in one of the vessels.

An additional challenge is the on-site reinforcement of the 26-year-old steel support structure, which has to be carried out according to the latest structural codes.

According to the information we have received, the demolition of the electrical systems in the L5 building has already been completed in the 1 and 2 aisles. The demolition of the reinforced masonry, which previously served as a fire barrier, is in progress, as well as the reinforcement of the steel structure and the basic mechanical-electrical installation in nave 2.

Work on the other hall is well advanced

magyarepitok.hu also received information about the construction of the L5B hall in Infeld: the project is on schedule, despite the extremely wet weather. The roof insulation work on the hall was completed on 24 November and the structural work on the internal social building was completed on the same day. The industrial flooring was also completed in the hall before the Christmas period.

At the same site, the trail construction works for the mechanical and electrical suspension fittings were completed. The installation of the thermoventilators is currently underway and the cabling work has started. The installation of the industrial gates is also underway and the finishing work on the social building has started.

As for the external works, the utility works are complete, while the road works are ongoing. As part of the project, an area of 2,400 square metres of paving stones has been completed to serve as a roll storage area.

This is the status of the fertőszentmiklós hall project

Also progressing well is VELUX's GP4 hall in Infőszentmiklós, where WHB is also on schedule. Here, the precast reinforced concrete structure of the 14,000 square metre hall building was completed on 17 November.

The bedding inside the hall, together with the soil stabilisation underneath, has been completed to a level of -0.25 m: this allows working on soil that previously had no bearing capacity.

The roof slab of the hall has also been completed, the roof insulation works have reached 50 percent completion and the installation of the lane lighting has started.

At the same time, the installation of the façade panels is underway, and is currently 90 percent complete. In nave 1, the mechanical and electrical installation is complete, while in naves 2 and 3, the same work is still in progress.

A lake and a park will also be created

Work is still ongoing on the utilities in the hall area, which is currently about 40 percent complete. The construction of the ground floor of the two-storey main building, with a floor area of approximately 500 square metres, is currently suspended due to the frosty weather.

As part of the project, a firewater reservoir pond was built, with a surface area of 360 square metres and a volume of around 750 cubic metres. The landscaping around the pond will continue in the spring, including landscaping, paving and additional design elements.

Source : Link