What is being built?

A temporary bridge to provide rail transport has been put in place in the Pest county town 

Published

A new underpass with a larger opening will help car and pedestrian traffic in Dunaharaszti.  

In Dunaharaszti, an outdated, narrow underpass is being rebuilt in connection with the construction of the Budapest-Belgrade railway line. The work is being carried out by Colas Út Zrt. on behalf of CTEC Kft..

László Holló, the company's construction manager, told our portal that the underpass at the junction of Némedi and Dózsa György roads, which has a 7-metre opening for both road and pedestrian traffic, will be rebuilt to a 13-metre opening.

The interesting feature of the project is that the railway line 150 between Budapest and Kelebia border crossing passes over the road, so during the construction phases the traffic necessary for the railway construction will be shifted several times on the existing and planned tracks.

The dimensions of the new underpass will be significantly improved

Construction work, which started in December 2023, involved the demolition of the existing road underpass to make way for a new, larger structure in all its elements. The works also include the construction of a storm water reservoir.

In addition to the 2×1 road lane, the new underpass will have a 13-metre opening and a separate lane for pedestrians and cyclists.

In addition to the opening of the underpass, we learned from the architect, the length of the underpass will also change significantly due to the fact that the underpass will be connected to the un. U-shaped section of the underpass between Gyárköz and Vasút streets. The aim of the reconstruction is to make the underpass safer and more modern.

Temporary bridge to ensure rail traffic

On 14 February, a spectacular stage in the construction was reached when a 450-tonne truck crane lifted the bridge provi-sory into place. This temporary bridge will ensure the continuity of rail traffic during the construction of the underpass, which is being carried out in several phases. The receiving substructure structures were completed before the bridge was lifted into place. Subsequently, with the construction of the track connections, rail traffic will be carried out on this provisorium.

Work is progressing as planned

The main phases of the construction, László Holló told us, are the delimitation of the working area, the construction of the closed frame (railway bridge), the construction of the open expansion units (U-frames) and the finishing works. The works are progressing as planned. The construction manager said that in addition to the implementation of the construction in several phases, they are facing challenges in coordinating utility replacements and structural works, as well as high groundwater.

Source : Link