Progress on the Zugló by Bayer neighbourhood is becoming increasingly impressive.

As we reported, in March, three buildings simultaneously reached their highest point in the new, multifunctional urban quarter of District XIV, where a residential building and seven office buildings are being constructed. The Bayer Property development, located next to Bosnyák Square, will be one of the greenest and most sustainable areas in Pest. Work is continuing apace and according to schedule on the Zugló by Bayer project, with more than half of the work, approximately 55-60 per cent, already completed by the contractor Bayer Construct Zrt.

A spectacular video shows the progress of the complex.

The only residential building in the development, Zenit, has already been completed and is expected to be handed over at the end of May, with the occupancy permit currently being processed. The 168 homes are equipped with modern technical facilities that help to minimise maintenance costs.

Accessible from three staircases (A, B and C), the eight-storey homes will have a single-level underground garage and ground-floor storage and parking. Shaded seating areas with benches and playgrounds have been created in the courtyards.

Seven buildings - in different phases

The seven office buildings are being built at the same time, with a slight time lag, so they are at different stages of construction. At the beginning of the summer, the project will enter a new stage: by June, the construction of two more office buildings - O3 and O4 - will be completed, Gergely Szalai, chief engineer of the Zenit by Bayer facility, told Szalai. He added that, in keeping with the usual meticulous organisation, the project is progressing very quickly, with the facades of three buildings already closed so that the interior work can begin.

At the beginning of March, three buildings celebrated their topping-out ceremonies: facilities named O1, O5 and O6.

Of these, the mixed-function O1 building is beginning to take its spectacular form: its prefabricated composite slab facade is already 70 percent complete. The basement level will house a restaurant, the ground floor and floors 1 and 2 will be used for retail outlets - supermarket, restaurant, bank, fashion and other services - and the upper floors will be used for offices.

Some are already designing the interiors

The fit-out of the O5 building is already underway. This includes the construction of suspended ceilings, suspended floors, interior finishes, basic mechanical-electrical installations. The same work will start in May on O6.

In May, the contractor will complete the underground work on the last building, O2, and the O7 building will be constructed on the second floor. This building is also scheduled to reach its highest point by August.

Source : Link