What is being built?
Almost only robots will work in Miskolc's new factory
The foundation stone for the Meleghy Automotive Hungary Kft. factory in Miskolc was laid at the end of September 2023, and the building responsible for product design and implementation is now complete. Weinberg ’93 Építő Kft. The project, worth approximately 9 billion forints, was supported by the state with 1.1 billion forints.
A factory worthy of premium customers was needed
Meleghy Automotive Hungary Kft. is one of the longest-established German automotive suppliers, having started as a family business around 100 years ago. Today, they have more than 1,500 employees at nine sites in four countries, with an annual turnover of €400 million and factories in the Czech Republic and Spain.
"The Miskolc plant was made viable by a major new business opportunity with a premium German car manufacturer, which has since been extended - to our great delight - by an agreement with another premium car manufacturer"
- Peter Katona, CEO of Meleghy Automotive Hungary Kft., told us.
The plans for the plant were based on a German greenfield project - also implemented by the group a few years earlier - but the complex in Miskolc is more modern and greener than that. The facility's special feature is its high degree of robotisation, which increases efficiency and quality while requiring a minimum of physical labour, around 50 people. From a labour market perspective, the company's main objective is therefore to develop a pool of engineers and technicians to operate the machines.
"Miskolc has a strong mechanical and electrical engineering background and knowledge base, which greatly facilitates the supply of skilled labour"
- added Péter Katona, adding that they will work with aluminium and metal here and will be important suppliers to the BMW plant in Debrecen.
"We were looking for a partner with a long track record and strong expertise. Weinberg met all the criteria and it is particularly pleasing that, as a local company, we were able to keep the economic impact of the project in the region, thus indirectly supporting local families."
A complex building was born
Krisztián Kollár, project manager of Weinberg ’93 Építő Kft., helped us learn about the production hall powered by renewable energy. The approximately 6,000 square metre building is located on a 33,000 m² site, which also includes 956 m² of outdoor space.
"The building consists of two main parts - a production hall and office space - with a clean design that matches the internal technology. We have designed four main masses: the office building, the hall, and the loading area covered by two side canopies," we learn.
Most of the architectural features are found in the office building: the entrance opens up to the outdoors with large glass surfaces and a canopy. The functions housed here (two-storey office space, changing rooms, storage, dining and mechanical rooms) require very different window layouts and façade openings, so the contractor built a "framework" to ensure a uniform appearance. This not only brings the entire facade together, but also allows for the use of different materials and colours to articulate the homogeneous building mass.
The two-storey lobby main entrance space is fully open, creating a strong visual connection with the exterior.
In the same way, monotony was avoided in the hall by subtly changing the materials and colours. "The investor wanted the building to be completed in a phased manner," said Krisztián Kollár. The main building and the hall part with nine pillars and the two side canopies will be completed in the first phase, while the eastward extension of the hall will be completed in the second phase."
Parallel working to speed up construction
Meleghy Automotive imposed a condition on Weinberg that the hall building should allow for a 24 m wide production area, within which three functional units were to be located: the production hall, the in- and out-going warehouses and external covered loading areas with parking and internal road network.
"The phased construction of the hall allowed the technological elements of the production to be installed in parallel with the architectural works"
- stressed the project leader. The contractors had to build a compressed air system and a cooling water network to supply the production equipment. In addition, a crane with a lifting capacity of 3.2 tonnes was installed in the production area of the hall, which the Weinberg workers had to take into account when constructing the supporting structure.
Despite the difficulties, the primary objective was still quality
"The particularly high ground water level was the biggest challenge during the construction, which accompanied the entire work process from the foundation to the utility and road construction" - recalled Krisztián Kollár.
"And the high organic matter content of the soil in the area," he added, "made it even more difficult to implement the planned technical content. Through regular on-site laboratory tests and analyses, the most optimal technical solutions were finally achieved; for this purpose, Weinberg was at the customer's disposal, in addition to the designers."
Another challenge was that the contractors had to carry out the architectural and civil works of the third phase in parallel with the installation of the technological systems by the co-contractor, sharing the workspace. As the project manager stressed:
"We were able to complete our tasks without any obstacles, in constant coordination with the staff of Meleghy Automotive, with weekly schedules. I must highlight in particular the flexibility and helpful attitude of the customer to the parallel work, thanks to which we managed to meet the deadlines without any technical problems or accidents."
Source : Link
-
Bound track 2026. 10. 07.
Aurora beneath the Apennines – Another tunnel is being built on the Naples–Bari railway line
-
Road building 2026. 10. 13.
A consortium comprising STRABAG and Duna Aszfalt has been awarded the contract to build the North Macedonian motorway
-
What is being built? 2026. 10. 09.
One of Budapest’s oldest nurseries is being renovated whilst preserving its timber roof structure
-
Current at 2026. 10. 10.
„The focus will not be on Lean’s equipment, but on how we operate” – the ‘Lean in the Construction Industry’ conference in November