Road building
The situation for truck traffic will be significantly improved with this road project in Eger
Most of the work has already been completed, so the renovation of Iparos Street in Eger will soon be finished, according to the company's announcement HE-DO csoport. The work area – for which the project was put out to tender by the local government of the city of Eger rel="noopener">Eger County Municipality and which was independently won by the construction company – was handed over to the experts on 3 April.
100 tonnes of crushed stone were installed in the embankment
Since then, work on the 350-metre long and 6-metre wide section has been carried out in two phases: the first phase between kilometre sections 0+110-0+345 and the second phase between kilometre sections 0+000-0+110. According to Zoltán Vidó the technical content of the road works is the same for both phases.
"After demolishing 1300 cubic metres of completely destroyed crushed stone track structure, we made 480 cubic metres of crushed stone bedding and built 720 metres of sunken kerb. We then constructed 370 cubic metres of concrete base and 580 tonnes of asphalt track structure in two layers. We used 100 tonnes of crushed stone to construct the double-sided embankment"
- said the Chief Architect of HE-DO.
They are already working on the Eger streams
In Phase I, 52 metres of plastic pipe and 140 metres of precast reinforced concrete trench lining were installed to drain the rainwater, and in Phase II, an earth ditch was constructed in the necessary places.
The HE-DO is currently working on the copper lining of the intake structure at Eger creek and the construction of the concrete stoplogs. Once these are completed, all that remains to be done is to complete the works on the containment structure, as well as debris removal and clean-up.
Why Iparos Street is important for trucks
The renovation, which will soon be completed, is of great importance as Iparos Street is one of the busiest service roads in the Eger industrial park.
"There is significant truck traffic from and to the industrial sites, plus external truck traffic from the truck wash and truck service on the street. The renovation will help site operators, workers and of course users of site services to travel safely and comfortably"
- explained Zoltán Vidó.
The complete road closure, which was set up in phases, was lifted at the end of June and the whole project will be completed by HE-DO at the end of July.
Source : Link
-
Kirakat 2026. 10. 01.
A leading machinery distributor in the construction and haulage sectors is building a new service centre and extending its existing premises
-
Industry news 2026. 10. 02.
Hungary has joined the single electricity market
-
Railway development 2026. 09. 29.
The railway line leading to the Hungarian border is also set to be upgraded as part of Croatia’s large-scale development programme
-
Bound track 2026. 10. 07.
Aurora beneath the Apennines – Another tunnel is being built on the Naples–Bari railway line