Painting of the pavement signs on the M6 motorway closure section could start soon

Published

The project, carried out by Duna Aszfalt and STRABAG, has completed the construction of the wearing course of the main carriageway on the section of the motorway up to the border.

We regularly report on the extension of the M6 motorway to the national border. The 20-kilometre section between Bóly and Ivándárda (national border) will have a crown width of 26.6 metres, with a physical divider in the middle and a paved hard shoulder, and will be designed for a speed of 130 km/h.

The project was commissioned by Építési és Közlekedési Minisztérium and carried out by Duna Aszfalt Zrt. and STRABAG Építő Kft. consortium, with a net contract value of HUF 88.6 billion.

The aim of the development is to improve transport along the Danube and in the Mohács region, and to provide a safe and fast service for transit traffic between northern and southern Europe. The construction of the missing section will complete the Hungarian section of the TEN-T corridor linking the Adriatic and Baltic Sea regions by road.

Construction of traffic engineering elements to start shortly

Gábor Boldizsár, the chief architect of Duna Aszfalt Zrt., Gábor Boldizsár gave information about the current status of the works.

"In August, the construction of the main track wearing course was completed. The construction of the remaining asphalt wearing courses - Villány junction, branches of the axle weight measuring station (TSM), and the factory exits - will be completed by mid-September. The construction of the TSM weigh house and social buildings is underway, as well as the assembly of the water treatment technology, for which the trial run will start at the end of September."

The expert also said that the technical handover and temporary opening to traffic of three national road correction sections - road 5704 and crossing bridge, road 5702 and crossing bridge, Lippo roundabout - have been completed, so traffic is now moving on the new sections.

The portal structures and the associated traffic displays have been constructed, and the operational communication system is under construction along the entire section and at the TSM station.

At the end of September, work will start on the traffic engineering elements - signs, pavement markings - and the construction of the barrier and wildlife fence will be completed.