Road building

Important step towards the construction of the new bridge in Szolnok

Published

Szandaszőlős, which belongs to Szolnok, can finally be freed from the transit concept.

Preparations for Szolnok's new bypass, which will reduce traffic congestion in Szandaszőlős, have been underway for years. Now, the public procurement for the preparation of the implementation plans has finally been announced. Based on the approval plans and building permits prepared in 2022-2023, the winner will be responsible for preparing the necessary implementation plans for the 0.5 km long inner-city section and 9.4 km long outer-city section of the new, continuous, 2×1 lane relief road.

A new bridge over the Tisza will also be built in connection with the bypass, which, according to information provided by Szolnok TV, will affect the floodplain of the Tisza, so the cross-sectional movement of wildlife must also be ensured. The bypass will connect to Vörösmező Street, and before that, it will be possible to turn off it towards Tiszaliget, and finally, it will connect to Martfűi Road via a multi-lane roundabout. The works are expected to be completed after 2027.

To the winner

  • Construction of 9.9 km of 2×1 continuous lanes of national road (secondary arterial road),
  • upgrading 0.5 km of existing national road (primary trunk road),
  • 6 km cycle path,
  • is a single level node,
  • two level nodes,
  • three roundabout junctions,
  • 5.3 km of intersecting and parallel dirt roads.

New bridge

The design task includes

  • two retaining walls and
  • the design of nine road bridges, of which
  • the Csáklya road embankment bridge over the Tisza river (with a superstructure length of 283.60 metres; spans 178.00+60.00+48.00 metres; bridge width: 20.18 metres), and
  • the design of the bridge over the Surge Canal (length of the superstructure 354 m; spans 52,00+4×62,00+52,00 m; span 20,18 m).

Source : Link