Road building

A curiosity: the mountainous section of the main road 25 is being improved with a new rampart

Published

The project will also include the construction of a bridge and a causeway, and will cover the territory of two counties.

One of the important transport developments in the north-east is progressing according to schedule: the 7.5 km section of secondary main road No. 25 between Kerecsend and Bánréve, between Szentdomonkos and Borsodnádasd, is being rebuilt. The construction work is being carried out by SWIETELSKY Magyarország Kft. and the HE-DO consortium, the project involves the complete renovation of main road 25:

  • In Heves county, between km 47+372 and 50+894,43,
  • And in Borsod-Abaúj-Zemplén county between the 50+894.43 and 54+184 km sections.

The entire section will be built with a fast lane, creating 2+1 lanes.

Area concerned by the investment

Due to the widening, experts will construct 16 gabion basket retaining walls on the cut side, as well as 12 reinforced soil retaining walls on the embankment side, which are considered a rarity in Hungarian projects due to their length. The company KM Építő Kft. is also participating in the construction.

A new bridge will be built over the Christmas Valley stream at section 54+046.41 km, and utility replacements will be made for drinking water, telecommunications and low and medium voltage power networks.

From summer 2025, traffic will be faster on trunk roads 23 and 25

"Prior to the construction works, we carried out site preparation (such as brush and shrub clearance, tree cutting, stump grinding and mowing) on about 190,000 m2. In Heves county, approximately 17.5 km of minor roads were designated as diversion roads, of which we carried out resurfacing works on about 10 km" - said Iván Farkas, project leader of HE-DO.

The Építési és Közlekedési Minisztérium project aims to improve road safety on the section concerned, reduce the number of accidents, improve the living conditions of the communities concerned (reducing noise, vibration and air pollution) and reduce the cost of vehicle operation for road users. The project will significantly reduce travel times between Bátonyterenye and Banréve on main roads 23 and 25 from summer 2025.

Source : Link