Road building
Hungary's biggest ever motorway upgrading programme continues
On Wednesday, this year's levelling work will start on the M7 motorway at three locations - the Kőröshegyi viaduct, Balatonlelle and Becsehely - with the construction of diversions. This week, preparatory work will also begin on the M7 to replace the damaged pavement, MKIF Magyar Koncessziós Infrastruktúra Fejlesztő Zrt.
Work will also start next week on the M3 motorway, the main part of this year's renovations on this motorway. On the M1 motorway, work will start after the holiday due to the increased traffic over Easter.
As last year, work on the M7 between Budapest and Lake Balaton will be suspended during the holiday period. The MKIF is carrying out renovations on nine motorways - M1, M15, M3, M30, M35, M4, M7, M70, M8.
Hungary's biggest ever motorway upgrade started last year and will last until 2025, covering 538 kilometres, 43% of the maintained road network operated by MKIF. Last year, 3.6 million square metres of old, deteriorated pavement was replaced, using half a million tonnes of asphalt. This means that 19 percent of the total main line was renewed last year, including 106 bridges and overpasses. This year, another fifth of the main line is expected to be resurfaced, and 110 bridges and flyovers will also be renovated.
In August last year, the renovation of the rest areas started, with the replacement of the buildings' mechanical systems, internal tiling, sanitary ware, doors, roofs, external facades and new furniture at the stops.
This year, some junctions will also need to be resurfaced. For this reason, there may be closures and diversions at several junctions until the end of this year's works, probably until November, MKIF pointed out.
Source : Link
-
Bound track 2026. 10. 07.
Aurora beneath the Apennines – Another tunnel is being built on the Naples–Bari railway line
-
Road building 2026. 10. 13.
A consortium comprising STRABAG and Duna Aszfalt has been awarded the contract to build the North Macedonian motorway
-
What is being built? 2026. 10. 09.
One of Budapest’s oldest nurseries is being renovated whilst preserving its timber roof structure
-
Current at 2026. 10. 10.
„The focus will not be on Lean’s equipment, but on how we operate” – the ‘Lean in the Construction Industry’ conference in November
