MKIF: The replacement of the Pentele bridge over the Danube at Dunaújváros starts
On the section of the M8 motorway between Dunavecse and Dunaújváros, maintenance work planned for this year will begin on the 1,682-metre-long Pentele Bridge over the Danube, which is essential to ensure that traffic continues to be safe , announced Magyar Koncessziós Infrastruktúra Fejlesztő Zrt. (MKIF) in a statement on Monday.
The half-lane closure will start on Tuesday, the statement said.
The structure, which was inaugurated in 2007, last had its mud replaced 13 years ago. During periodic bridge inspections, anomalies were found in some structural elements that adversely affected the expected life of the existing spans. Therefore, the replacement of several of the piles and the dilatation structure has become necessary this year.
The MKIF specifically pointed out that the bridge is currently in a safe and stable condition, but as with any engineering structure, parts of a bridge can wear out. Bridges under the company's management are regularly inspected by bridge engineers.
On the Pentele bridge - which is actually a group of five separate steel bridges - a total of 13 spans now need replacing. 10 on the floodplain bridge and 3 on the bascule bridge
- were presented.
For precise information on the works
They also point out that in recent weeks there have been several untrue reports in the press, not coming from us, about the planned works on the bridge and its closure, so they strongly and repeatedly ask for:
With regard to the work being carried out on the network sections operated by MKIF Zrt, only news items that have been officially written in a letter by the company, published in a press release or posted on the company's social media platforms, websites.
Three phases for the one-and-a-half-kilometre-long bridge
To carry out the work, traffic will be restricted in three phases: on the southbound side, half-lane closures will be in place from Tuesday until the end of May, with a total of three weekends in April and May. There will also be a full closure on the northbound and southbound lanes throughout June. On the northbound side, there will be a half-lane closure from 1 July to the end of August.
In addition to replacing the bridge spans, the dilatation structures of the bridge will also be rebuilt. In order to install the new dilatation structure, the old one will have to be removed from the pavement. The bridge is therefore expected to be closed across its entire width from 1 June to 30 June. The diversion route has been designated towards Dunaföldvár, so it will be possible to cross the river between Dunaföldvár and Solt on the main road 52 during the closure, the concession infrastructure developer said.
Source: Link
-
Industry news 2026. 08. 18.
Students were introduced to the high-tech construction industry at BME’s field camp in Göd
-
Bound track 2026. 08. 17.
New pedestrian crossings and a junction with traffic lights are being built in Angyalföld
-
What is being built? 2026. 08. 18.
Hungary’s new McDonald’s restaurant has moved into a modernist listed building in the centre of Budapest
-
What is being built? 2026. 08. 18.
New paving, a playground and visitor facilities are being planned for the Várkör area in Pannonhalma