Water management

One million cubic metres of reservoirs will be added to the irrigation system of South Baranya

Published

The SZABADICS Group and the AQUAPROFIT can run the irrigation network of Baranya from Mohács to the southern border.

Thousands of hectares of farmland affected

More than ten years ago, in 2014, one of the largest irrigation capacity developments in South Baranya was built: the 1,037-hectare irrigation plant on the outskirts of Sátorhely, Nagynyárád and Kölked was commissioned. The project involved the construction of a number of large-scale facilities, including

  • a pumped water intake was installed on the Danube (Mohács) with a capacity of 2,880 m3/h,
  • a 6,477 m long supply pipeline (DN700 penstock) was built,
  • A 30,000 m3 insulated reservoir was built,
  • an irrigation pumping station with a capacity of 2,489 m3/h has been set up,
  • 1.037 hectares of irrigation land was born, with 19 centre pivot irrigation systems from a network of underground pressure pipes and
  • 1.545.000 m3/year.

As a continuation of this, as can be seen from public procurement data, you can now build the SZABADICS Group and AQUAPROFIT Tervező és Építő Zrt. irrigation plants in the Ormány and Kislippó areas. In 2023, with the involvement of land users farming in the area, Ormány Öntözési Kft. and Kislippói Öntözési Kft. were established. These irrigation communities, utilising the spare capacity of the existing Danube water supply system, began development based on the plans of NAVASTART Kft., affecting the outskirts of Bezedek, Majs, Lippó, Márok, Kislippó, Ivándárda, Illocska and Magyarbóly. The irrigation developments of Bóly Zrt., Ormánypusztai Irrigation Kft. and Kislippói Öntözési Kft. were implemented in several phases. The contractor is expected to complete the aforementioned investment affecting the Kislippó area on 31 July 2025.

Utilisation will increase significantly

The almost 12 km long underground supply line, to be built in cooperation between Ormány Öntözési Kft. and Kislippói Öntözési Kft., will supply the Danube water to the surrounding land, subject to obtaining all environmental, water and heritage permits,

In addition to the necessary irrigation works, a one million cubic metre insulated reservoir will be built in Ormánypusztan and Kislippo.

As summarized by project manager László Fischer in response to our questions, the tasks supporting the environmentally friendly irrigation among the tertiary water supply works

  • a feed pump is installed at the 30,000 m3 insulated reservoir Bóly Zrt. with a capacity of 720 m3/h,
  • the T1 and T2 supply lines will be installed, for a total of 11,561 metres (DN500 penstock),
  • In Ormánypuszta and Kislippo, one million m3-insulated reservoir will be built.

In addition, the contractor will also be responsible for the construction of irrigation facilities in Ormánypusztán

  • a pumping station with a capacity of 1,386 m3/h will be set up,
  • 340.7 ha of irrigation land is supplied with 5 centre pivot irrigation systems operated from 4,257 m of underground pressure pipe network.

While in Kislippo

  • a pumping station with a capacity of 1,055 m3/h is built,
  • 345.1 ha of irrigation will be constructed with 7,431 m of underground pressure pipelines, with 7 centre pivot irrigation systems.

Source : Link