Important development at our largest natural gas storage facility completed with continuous operations
A strategically significant development was carried out by Vabeko Kft. has carried out a development of strategic importance at the underground gas storage facility in Zsanai operated by Magyar Földgáztároló Zrt. (MFGT). Our newspaper obtained information about the project from a leading company in the Hungarian gas industry and MFGT.
The largest container was the last to be completed
There are four underground gas storage facilities in Hungary, located near the towns of Pusztaederics, Kardoskút, Hajdúszoboszló and Zsana. The four facilities of Magyar Földgáztároló Zrt. represent a total of 4.43 billion m3 of continuously available mobile gas storage capacity, with the Zsana facility being the largest with a capacity of nearly 2.2 billion m3. As we previously in our article on the Pusztaderics storage facility, natural gas storage in Hungary is primarily carried out in the remaining porous layers of depleted underground gas fields, i.e. depleted natural gas fields are converted into underground gas storage facilities.
Of the four storage facilities, the first one in the Kardoskút area was established in 1978 by converting partially drained natural gas fields, and in 1979 the storage facilities were put into operation in Hajdúszoboszló and Pusztaederic. The fourth storage facility was at Zsana, where construction started in 1992 with the conversion of the former Zsana gas storage facility.
Storage at a depth of more than one and a half kilometres
After several expansions, the continuous mobile gas capacity of the Sasana storage facility is 2,170 million cubic metres, with a daily withdrawal capacity of 28 million cubic metres per day. (As indicated earlier, in the withdrawal process, gas injected during storage is extracted from the storage layers through production injection wells - editor's note) Due to its geological characteristics (limestone storage), this storage facility is the most flexible natural gas storage facility in Hungary. Natural gas is stored at a depth of 1695-1780 metres below sea level.
As previously reported, the Vabeko Kft. is involved in all domestic storage works and has been carrying out maintenance and development work on these since 2011. The Hungarian company has permanent staff in all the storage facilities, but in case of need, i.e. for large-scale construction activities, they send workers and equipment from their central staff to the site.
What happens if further extraction becomes necessary with severely reduced reservoir pressure?
As a precursor to the work under consideration, MFGT has carried out an internal study at the Zana storage facility to assess a situation where further extraction would be necessary in the event of a gas supply crisis, for example, with the storage pressure at the end of the withdrawal reduced. Should it become necessary to continue the withdrawal even at low storage pressure, the following steps have been examined by MFGT to assess the feasibility of doing so:
- How far can the pressure in the storage facility be reduced to allow the gas to leave the storage facility "on its own" to the FGSZ system?
- For how long and under what conditions can the storage be operated if FGSZ Földgázszállító Zrt. as a partner reduces the zero point pressure on the Zsana-City Ground pipeline by starting the City Ground compressors?
- Under what operating modes and parameters can the existing NEA compressors assist in evaporation, and under what conditions can this operating state be maintained?
Pipe sections in three places had to be relined and fitted with sectioning equipment
One of the key findings of the study was that the minimum delivery capacity of the existing Siemens compressors (in discharge mode) is also too high compared to the well capacities available in low-load storage.
As a result, it was decided that in the situation described above, the existing NEA reciprocating compressors would be used to perform the boosting tasks. To this end, longer and shorter pipe sections had to be connected at three different points in the technology by means of a tie-over and a sectioning fitting.
The work of experienced professionals was needed
In accordance with the above decision, the Vabeko Kft. has been designed with the NEA compressors' connecting wires rewired to provide the evaporative mode. In doing so, the report submitted to our journal identified as a particular challenge the execution of the pressure drilling on the DN 800 PN73 suction header, which had to be carried out during operation. "This meant that the gas storage facility's shut-off operation was continuously ensured while our experienced welding colleagues welded the two-part saddle nozzle onto the pressurised, operating pipeline," the report reads.
They added that a flange was mounted on the two-piece boom, on which a T.D. Williamson type drilling rig was mounted. "The equipment drilled through the base tube without any problems using a crown drill of the correct size. Thanks to this, one of the most important operations was carried out while ensuring the uninterrupted gas supply," they stressed.
An equally significant task was the cutting of the 610×45 mm vertical section of the pipeline and the welding of the connecting section with the fitting. "The most challenging part was the cutting operation and the welding of the thick-walled pipe sections," the report concludes.
Source : Link
-
Bound track 2026. 10. 07.
Aurora beneath the Apennines – Another tunnel is being built on the Naples–Bari railway line
-
Road building 2026. 10. 13.
A consortium comprising STRABAG and Duna Aszfalt has been awarded the contract to build the North Macedonian motorway
-
Current at 2026. 10. 05.
Sofitel Hotel is the only Hungarian project in the running for the Dalux Award 2026 award – Watch the video too!
-
What is being built? 2026. 10. 09.
One of Budapest’s oldest nurseries is being renovated whilst preserving its timber roof structure