Industry news
New building law enters into force
Act LXIX of 2023 on the Regulation of Public Construction Investments was published in the Hungarian Gazette No 154 on 31 October, and according to its Article 60, it entered into force on the 8th day after its publication, i.e. on 8 November.
Thanks to the legislation, a single law now applies to all public works projects. The law applies to all projects that are at least 50 percent financed by Hungarian budget or EU funds.
Our newspaper previously analysed the draft bill in detail, which, based on its strategic elements, could tune the construction industry to operate in a more conscious manner. At the same time, we also conducted a lengthy interview with Regő Lánszki, State Secretary for Architecture and Chief Architect of Hungary, about the elements of the new regulations, analysing the new public investment law as well as the architectural law that is still in the process of being drafted.
Presenting the law in Parliament in July, János Lázár, Minister of Construction and Transport, said that the law guarantees predictability for those involved in construction, and aims to ensure sustainability, low environmental impact and cost-effectiveness. He called the legislation a patriotic one, aimed at involving domestic small and medium-sized enterprises in public investments.
The stated aim is to ensure predictability for investors
The new law, which has just been promulgated, contains five chapters and 82 articles on public works. Its objectives, as stated in Article 2:
- help ensure efficient implementation of public investment and provide predictability for investment actors;
- strengthen the transparency of public construction investments, with particular attention to investment costs;
- define the roles of the participants in public works and their relationship with each other;
- to lay down the basic rules for public works, from preparation, design, construction, operation and maintenance of the resulting works, taking into account the requirements of cost-effectiveness, efficient and effective use of budgetary and EU resources, and environmental sustainability.
Source : Link
-
Road building 2026. 10. 13.
A consortium comprising STRABAG and Duna Aszfalt has been awarded the contract to build the North Macedonian motorway
-
What is being built? 2026. 10. 09.
One of Budapest’s oldest nurseries is being renovated whilst preserving its timber roof structure
-
Current at 2026. 10. 10.
„The focus will not be on Lean’s equipment, but on how we operate” – the ‘Lean in the Construction Industry’ conference in November
-
Current at 2026. 10. 13.
It’s time to provide information to those in the sector – that’s what this year’s Építőipar Summit was all about