Three major projects in the capital's transport development could be launched next autumn

Published

In total, almost 50 kilometres of new HÉV lines will be built, with construction contracts for H5, H6 and H7 all due to be signed by the end of September 2024, according to the new EU timetable.

The renovation of three suburban HÉV lines may begin in the third quarter of next year. The development plans for the H5 Szentendre line, the H6 Ráckeve line and the H7 Csepel line can be found at Portfolio reported in detail, referring to the EU data that was made public.

Construction to be completed in less than two years

The paper recalls that the European Commission has approved Hungary's amended and supplemented recovery plan, and the Brussels body's working document lists the points of the original programme adopted last year that the government requested to be amended. At the same time, the article refers to the European Commission's 294-page detailed assessment of the Hungarian recovery plan, which also presents an updated schedule for the renovation of the HÉV lines.

According to this

  • By the third quarter of 2024, i.e. the end of September, the concrete construction contracts for the 46 km of upgrades on all three lines will be concluded after the public procurement procedures have been completed;
  • By the end of 2025, the technical completion of 50% should be achieved;
  • All projects have to be completed by the end of June 2026, which is justified by the fact that the recovery programme can only be used to cover the costs of works that will be completed by then.

Major improvements to trams and trolleybuses

However, the amendments presented in the above-mentioned Brussels working document also reveals that the EU budget for the modernisation of the three suburban HÉV lines has been reduced from EUR 698 million to EUR 515.6 million, i.e. by EUR 182.4 million. According to the summary, this has also led to a reduction in the overall technical commitments for the projects. According to the new data, overall

  • 46 km of lines and tram network will be upgraded;
  • 10 stations are being upgraded and upgrades are being made to allow barrier-free access;
  • The government will build 1000 P+R parking spaces around each stop;
  • 1500 B+R bicycle storage facilities will be created;
  • three intermodal hubs will also be built, allowing passengers to make direct connections between buses and trains.

In addition, two new Budapest transport projects have been included in the newly approved recovery programme: one for the purchase of 51 trams and trolleybuses for €147.1 million, and the other for the related infrastructure for €106.5 million.

Source : Link