What is being built?

A unique mobile sound barrier wall is being built at the NFI film studio in Fót, Hungary

Published

During the construction of the consortium Market and Fejér-B.Á.L., the operation of the complex must be ensured at all times.

In December 2022, reported that the expansion of the NFI film studio in Fót was halfway complete. The construction was carried out by Market Építő Zrt. and Fejér-B.Á.L. Zrt..

The biggest ever publicly funded studio development will see the construction of four new studios (actually 2 large separate and separable studios) and support facilities. The expansion of the studio complex will add a total of almost 10,000 square metres of usable floor space to the current 2,692 square metres of studio space, bringing the total to 12,582 square metres available for productions in Fót.

In connection with the progress of the project, we contacted Market Építő Zrt., represented by Görgy Gaál, chief architect.

"An important aspect of the project was the need to ensure the continuous operation of the film factory, as there were several film shootings during the project. The commissioning of the buildings completed in the first phase of the project is under way. The technical hand-over of the service and storage buildings has been completed and the film production units (sculptors, locksmiths, painters, carpenters, a company providing film trailers) will move into these buildings.

In addition to the above, the road, utility and electricity network development works in the area are at an advanced stage. The final transformer stations have been installed, the new utility network (fire water and drinking water system, storm and sewerage) and the new road network are at completion of about 75 %."

Existing buildings will also be renovated

The steel support structure of the studios is now complete. The structural work on the adjacent main building is also complete, and the trades are currently underway. It will also house offices, small workshops, make-up rooms and dressing rooms.

The catering buildings have reached structural completion and are expected to be handed over in the next phase, at the end of autumn. The façade windows have been installed, the cold coating and painting work is currently underway, the basic mechanical and electrical installations have been completed and the lifts have been finished.

For the two porter buildings, the specialist works are currently underway and the buildings are scheduled to be handed over by the end of the year.

Renovation work on the existing buildings will start in the second half of the year, after the new service buildings have been brought into use.

Due to the constant filming, work organisation requires a lot of attention

In response to our question about the special architectural, technical and technological solutions used in the construction, the chief architect said:

"The steel structure of the two studios is unique. The mobile sound-barrier wall separating the studios is 14.5 metres high, a height that has never been achieved in our country, and the sound-barrier gates used in the studios will be technically and technologically interesting.

The biggest challenge is the organisation of the work, given that we have to ensure the continuous operation of the plant during the construction. There were several shoots where we had to interrupt the daily work for 15-20 minutes during the shoot, up to 10-15 times a day. It required a lot of patience, both on the part of the people working on the construction and the people working on the filming."

The expert concluded by adding:

"In the coming period, the construction of the steel structure of the interior soundproof walls and the installation of the wall will follow, as well as the catwalk and mother grid system, which will be installed after the studios are covered, and the mechanical, sprinkler and electrical installations under the roof will be a major organisational task. This will be done by scaffolding the mother grid system in several phases to ensure a safe working level for the workers."

Thanks to the comprehensive development, the NFI studio complex in Fót will become a key element of film production both internationally and domestically, and its operating costs will become more economical. In addition to new construction, the project will also include the renovation and upgrading of existing buildings, the energy system, internal roads and utilities.