Zugló's new, unified buildings also have a unique character
The facades of the buildings in the Zugló ZVK project were selected for sampling. The Bayer Construct Zrt. project involves the construction of seven office buildings and one residential building (all with AA++ rating) using efficient, accelerated construction and precise organisation.
From the very first plans, the buildings had a unified look. The developer, the designer and later the builder sought to achieve this uniformity in the facade selection process, while also striving for some variety.
The choice of shape and material had to meet several criteria. In order to speed up construction, they were looking for a structure that was lightweight, easy to install and at the same time durable. The glass surfaces of the opening shutters had to be selected to meet energy requirements.
Cost is a key element of development, and can be reduced through an efficient, accelerated construction process. Imre Harmat, development director of the Bayer Property Zrt. explained to our newspaper:
"Ninety-five per cent of the elements are made in a factory, then assembled in a workshop, then simply lifted and fixed on site. This reduces the construction time of the façade to about 2/3 of the time of the traditional curtain wall process. Prefabrication, controlled under workshop conditions, in line with the construction schedule of the buildings and with precision, is becoming a basic requirement of today's building technology, and the Bayer Group is committed to this way of organising construction."
Of the options on the market, composite panels were finally chosen, as they offer high technical and aesthetic quality and creative architectural possibilities. The weight ofmetal is extremely light, easy to process and install, and provides an aesthetic appearance.
Imre Harmat also talks about the selection of the facade elements in a video made on site.
A long search for the right manufacturer
After lengthy technical discussions, ideal geometries have been defined that are suitable for both production and installation. Optimally sized overhangs are designed to cast shade. As a result, a grid system was developed which allowed the installation of shading dividers and framing for the monitor surfaces. In addition to the glass statics, the watertightness and grading of the cantilevered projections also had to be constantly taken into account," Gergely Szalai, project manager of the ZVK development in Zugló, told us.
"Once the detailed parameters had been agreed, it was just a matter of finding the right partners to design and manufacture the façade elements. We surveyed the domestic and foreign manufacturing markets. The ZVK's fast-paced buildings require huge quantities of structures - nothing like this had ever been produced on such a scale in Hungary. Therefore, we had to look for a company or companies that had worked with similar elements, even if not on such a scale."
In total, four such companies were identified by the team of contractors, engineers and developers, with whom they worked on the final technical design.
"Prefabricated facades are usually installed afterwards, using a lifting system and alpine technology, but as this process was found to be too slow for the ZVK schedule, we had to design composite elements with a system that would take their final shape on the production line. The organisation and design of these took an enormous amount of engineering hours", the project manager explained.
The contract was finally awarded to three Hungarian companies: KÉSZ Metaltech Kft., Nordical and Schaltec. Although they are competitors in the market, the Bayer Construct Zrt. contract encourages them to work together. Indeed, the amount of slab structures needed for the eight buildings of the project in zugló in a short timeframe could not be produced by a single company.
Glass is an important factor in energy efficiency
In addition to speed and quality, energy efficiency was also a priority. The eight buildings of the project in zugló have a total facade area of around 60,000 square metres. Only part of this will be made up of composite elements, the other part being glass, which was also a key factor in the choice of the material.
In modern architecture, glass is the weakest link in terms of energy and thermal performance, and it will become an important parameter of buildings, said Imre Harmat, development director of Bayer Property Zrt.. "Glass technology has undergone an amazing development in recent times. Today it has reflective, heat reflective, light transmitting capabilities that were unimaginable 15 years ago. The structure and the use of materials have evolved a lot, and tremendous progress has been made with the use of films and different gases."
One important task was to meet the energy performance requirements of the AA++ building certification.
"For office buildings, double glazing is usually used for element facades. The Bayer Construct is the first to use triple glazing. They are much heavier and more expensive, and take longer to produce, but their insulating performance is much higher, and we didn't want to compromise on that."
A sampling of the façade was presented
The project's mock-ups were used to visualise the selected facade elements at one storey height. Based on a sample of six elements, each 1.35 metres wide, the experts were able to look at the junctions, the advantages and disadvantages of the installation technique and the elements to be improved. Architects and developers could observe the overall effect of the panels, the profile and the glass. These had been approved individually before, but the whole was only now becoming visible.
The façade will be similar on all the buildings, and the choice of the slab was important because it is the dominant architectural motif of the whole project. It is the very face that puts its stamp on the visual image.
The original master plans gave the buildings a rusty base colour. With minimal modification, this colour has been carried forward by FBIS, the generic architectural design team that has further developed the original master plans. They designed identical buildings in the same colour, trying to emphasise the harmony between green as nature and the built environment, with a certain degree of playfulness.
The interesting thing about the chosen colour is that it plays with colours from bright orange to deep brown, depending on the angle at which the sun is shining on it, or when it is in shadow, or when there is a cloud in the sky.
The buildings are rotated relative to each other, and the plates are also rotated in the direction of the fibre, so two buildings next to each other, or even two adjacent surfaces, will not necessarily give the same colour. It will look completely different in the early morning sunlight than it does in the evening.
The facades of the buildings are very similar, but each has a unique character, and that is the lobby. The paving elements that extend from here to the main entrance area are accentuated paving forms that define the specificity and uniqueness of the main building.
The way forward
At the sampling stage, the experts approve the individual elements and the colour, after which production can begin. The composite panels ordered are delivered to the manufacturer in whole sheets, the profiles in full lengths and the glass in customized sizes. They are cut to size and then assembled into elements of the correct size according to the design.
They are then transported to the construction site and installed - on pins placed on the facade. They are fitted with water seals and gaskets to make the building watertight.
The width of the facade grids is 135 metres and the height varies according to the height of the floor. The seven office buildings (O1-O7) will have a total surface area of 51 428 m2 of element facades.
Source : Link
-
Bound track 2026. 10. 07.
Aurora beneath the Apennines – Another tunnel is being built on the Naples–Bari railway line
-
Road building 2026. 10. 13.
A consortium comprising STRABAG and Duna Aszfalt has been awarded the contract to build the North Macedonian motorway
-
What is being built? 2026. 10. 09.
One of Budapest’s oldest nurseries is being renovated whilst preserving its timber roof structure
-
Current at 2026. 10. 10.
„The focus will not be on Lean’s equipment, but on how we operate” – the ‘Lean in the Construction Industry’ conference in November