What is being built?

The gymnasium will be added to the high school in Tatabánya, which is being converted from the Mining Hospital

Published

Students at St Margaret's High School are benefiting from the work of EBH Invest.

An educational development project in Tatabánya may continue. After students were able to start using the building of Szent Margit Grammar School, which was created by saving the approximately 120-year-old Mining Hospital, in September 2022 (as reported by vasarnap.hu reported), the contractor for the next phase has now been found a contractor for the next phase: EB Hungary Invest Kft. The work will be carried out at a net cost of approximately 1.134 billion forints.

The first phase was completed as follows

In accordance with the original tender, during the initial works (which we wrote about in more detail here) only the structural framework of the gymnasium was built by the consortium of ZIB Komplex Kft., Valid Solution Kft., Octopus Invest Kft. and Rabel-Dekor Kft.. Now, EBH Invest can complete this part of the project: so that students will also be able to take possession of the sports building.

The plans for the conversion into a high school were previously drawn up by László Damokos, the chief architect of Tatabánya. The first phase involved the demolition of a number of dilapidated buildings on the site and the restoration of the hospital's locally listed facade. Behind it, there are now around 400 pupils in the 12-class, six-form St Margaret's Grammar School.

Construction in figures

The photo taken in March 2022 shows the first phase of construction nearing completion and the structure of the sports hall affected by the new project (source: János Bencsik/Facebook)

To complete the gymnasium, a significant amount of work is needed, as summarised in the EU procurement notice:

  • around 2560 square metres of screed will be laid,
  • 371 square metres of concrete and reinforced concrete structures are repaired,
  • 14820 square metres of ceiling and side plaster are completed,
  • 1317 square metres of suspended ceiling to be built
  • the PVC sports surface covers 1058 square metres,
  • 90 windows and doors are installed
  • 12415 square metres of surface preparation work will be needed
  • and 462 square metres of partition wall will be built

In addition, they also carry out mechanical installations, including water, sewerage, heating and ventilation networks. All this is expected to be completed in 9 months.

Source : Link