What is being built?

Another building supports Balatonfüred's two centuries-old bathing culture

Published

The VEMÉV-SZER can build a new cabin building on the most elegant beach of Lake Balaton.

The bathing village of Füredi is more than two hundred years old, as there was a small bathhouse here already in the 1820s, which was built by the Benedictine order despite the contemporary belief that the water of Lake Balaton would make your skin wrinkly. However, the gradual change in attitudes in the 19th century also brought the popularity of Lake Balaton. This was helped by the legendary water level in 1863, which was so low due to the extreme drought that even the oldest people cannot remember a similar event. Taking advantage of the drying up of the shores, they built up the shore over the next few years and created what is still perhaps the most popular walkway on Lake Balaton, the former Deák promenade, later renamed Tagore promenade.

In June 1889, the next big event in the life of Balatonfüred took place: the opening of the bathing season, when the public could use the modern bathhouse designed by Győző Czigler, the largest on the shore of Lake Balaton. These bathhouses covered the shores, but nowadays only in Keszthely can we see the original building. The new 12-towered bathhouse was 100 metres long, with an elegant waiting room and 90 changing rooms, and the lines written by Gergely Czuczor but attributed to Sándor Kisfaludy have become legendary:

"The beautiful strength of your soul is trained by the waves of fate. This lake gives your body a cheerful vigour."

450 metres to serve the relaxation seeker

During the Second World War, the bathhouse was used as an ammunition depot, which was completely destroyed by a bombing raid. Its spiritual heritage, however, is carried on by the Esterházy Beach, considered the most elegant bathing place on the Balaton shore. It offers bathing beaches, a beautiful panorama of Tihany, a favourable pool design and a lido with a beach with a lidos. The beach at the eastern end of the Tagore promenade is the regional leader in terms of appearance and maintenance, with a 450-metre-long beach, 29,000 m2 of landscaped recreation area and 60,000 m2 of bathing water.

A building tailored to contemporary needs

A cabin building can now be constructed on the eastern side of the beach by VEMÉV-SZER, where the project began in early February 2024 with the partial demolition of the former changing room building , according to György István, chief construction manager. In its place, a new two-storey changing room building measuring approximately 34 x 14 metres will be built with a mixed reinforced concrete and brick structure.

"The main purpose of the building is to provide a high level of service for beach-goers in the areas of changing and cleaning, as well as storage, storage and toilet facilities for the staff," the chief architect said.

At the moment, the preparatory works for the concreting of the reinforced concrete slab of the eastern wing and the central part of the building are in progress, as well as the formwork and reinforcing steel installation, on behalf of the client PROBIO Zrt. from Balatonfüred, but as we have learned:

"Concreting of the reinforced concrete structures (pillars and walls) on the west wing floor and masonry work on the structural ceramic walls are also underway. The masonry of the ground floor partition walls of the east wing and the electrical installation of the basic installation have also started."

Construction progressing well despite difficulties

The formwork, reinforcing steel installation and concreting of the reinforced concrete slab of the west wing will follow shortly, and the ground floor partitioning and electrical installation works will continue. It is planned to start plastering the ground floor side walls in June.

Working directly on the shores of Lake Balaton is always a challenge because of the high water table.

"This was also the case in our case," said István György. There is already 10-15 cm of ground water below the construction level, so during the excavation and concreting of the block foundations, water had to be pumped out of the foundations continuously so that they could be concreted. The high water table also made it difficult to move the machinery, as we had to work in mud all the time. In such cases, it is always a success when we 'get out of the ground', i.e. the construction of the base beams and base plates starts."

And in early March 2025, the newest building of one of the oldest bathing resorts in the Balaton region will be ready to open to the public.

Source : Link