What is being built?

The expansion of the Székesfehérvár hospital is about to reach the finishing line with the landscaping of the park, road construction and renovation of the connecting corridor

Published

Preparations are already underway for the commissioning of the building's mechanical and automation systems in the inpatient block built by Fejér-B.Á.L. Zrt. and Épkar Zrt..

The most important investment in the entire region may be built by Fejér-B.Á.L. Zrt. and Épkar Zrt. consortium in Székesfehérvár. We are continuously monitoring the construction of the new wing of the Fejér County St. George University Teaching Hospital. The construction of the internal medicine centre, with a total area of more than 6,100 square metres, is slowly coming to an end. Szabolcs Cser, project manager of FEJÉR-B.Á.L. Zrt., informed our newspaper about the current tasks.

Trial run at the "L" building

The interior windows of the "L" building have now been installed, the electrical and mechanical installations have been completed, the furniture has been installed and the painting of the rooms has been finished. The lifts and the necessary post-occupancy works have also been completed. The structural work on the external façade of the canopy has been completed and the parking area in front of the main entrance to the "L" building and the 40-space car park have been paved.

"At the moment, the commissioning of the automatic systems of the electrical and mechanical equipment and the preparation for the operational tests are underway", Szabolcs Cser told us.

In the connecting corridor between buildings DT and C, renovation work is continuing, with locksmithery and window and door installations and painting still to be carried out by the contractor.

The link corridor is being renovated with great effort and attention

"The renovation of the connecting corridor has reached a stage that will have a major impact on pedestrian traffic and the transport of materials and patients. As the corridor under renovation carries significant traffic and is essential for the operation of the hospital, its upgrading requires constant communication, increased attention and a major organisational challenge for colleagues"

- said the project manager, adding that every effort will be made to ensure the smooth running of the hospital during the works.

At the end of July, the rough landscaping, humus spreading and tin-plating of the canopy of the "L" building will start, together with the finishing works on the façade cladding. The construction of the pavements and paths around the building and in the park will continue, as will the gravel filling of the inner courtyard. Rough pipe cleaning is also expected to begin in early August before the start of commissioning.

"From July 15, 2024, due to the partial shutdown of the operating theatre, we will start the replacement of the windows, the cold coating and the interior painting of the connecting corridor between the "Hotel" and the "DT" building, which we expect to complete by August 15, 2024."