The replacement of the spurs on the Kőröshegy viaduct is proceeding as planned
On 2 September, work began on replacing the bearings on the Kőröshegy viaduct on the M7 motorway. Hungary's longest bridge and Central Europe's largest viaduct was opened to traffic in August 2007. No similar intervention has been necessary in the past 17 years, and this is the first time that the bearings on this bridge structure are being replaced. As reported by MKIF (Magyar Koncessziós Infrastruktúra Fejlesztő Zrt.) announcement on 26 August emphasised: the replacement of the bearings is a planned operation, and the bridge is safe and in good condition.
The work, which requires a high degree of precision, can only be carried out on a bridge closed to traffic, so the structure has been closed for two weeks, as planned, and traffic will be diverted.
The structure of the bridge has to be lifted a few centimetres away from the piers: in other words, the bridge is practically lifted out of its place.
Our crew had the opportunity to take photos of the event, which is quite rare, and the MKIF communications directorate informed us about the details and significance of the work.
The bridge is safe, it is actually a maintenance
The annual bridge inspections and the biannual bridge inspection, as well as the results of the spring test lifts, showed that 3 of the 38 spans on the bridge were worn and needed to be replaced.
The aim of the repair is to ensure that any wear and tear that may occur does not cause problems in the future. The bridge is constantly exposed to heavy loads, so such maintenance work is essential. Replacement of the bridge deck guarantees the safe operation and stability of the bridge for decades.
The spurs are special elements of the bridge
The hinges allow the bridge structure to move in a controlled manner, ensuring the stability of the bridge. They can support up to 4500 tonnes of weight each when in place. They measure 2x2x0.35 metres each and weigh almost 10 tonnes.
The new cranes have similar parameters to the old ones: they are identical in size, technology and load capacity to the cranes they replace. The tests carried out prior to the replacement did not justify the installation of stronger hinges, according to MKIF.
They use precise technology
A total of 18 hydraulic jacks with a lifting capacity of around 10,000 tonnes work simultaneously, synchronised with each other, with millimetre precision. The precise steps for each crane change are carried out in the following sequence:
- first, the jacks work in sync with each other to raise the bridge structure a few centimetres,
- the old mud is then removed,
- after cleaning and checking these surfaces
- the new hinge structure will be raised to a height of about 70-80 metres, and then
- after positioning, it is inserted.
- The new mud is subjected to a load test,
- finally, welding work is carried out, if necessary.
Other, parallel work is also underway
But that's not all: in addition to the replacement of the hinges, the anti-corrosion coatings of the expansion joints will be renewed in the entire cross-section - in 4 places - at the same time. And when there is no more traffic on the bridge, the MKIF Zrt. will carry out all the other tasks and renovations that it can.
Asphalting and embankment repairs are also underway on the closed section, speeding up the levelling of the track. The company's staff will also carry out repairs to the ribbon barrier and light barrier netting on the affected section, which would otherwise restrict traffic.
On the Kőröshegyi Valley Bridge, MKIF will continue to carry out a bridge inspection every six months, a bridge inspection every year and a so-called geodetic inspection every ten years. No special technology is required for the annual inspection of the bridge. The upgrade, which started last year, will not only replace deteriorated pavements on 538 km of motorways across the country by 2025, but also renew around 200 bridges and flyovers, including several major bridges such as the Kőröshegy Valley Bridge.
Serious preparations preceded the work
The technology and workflow of the entire replacement was planned by the experts in preliminary coordination meetings. In case the execution of the work processes deviates from the planned one, MKIF Zrt. corrects the implementation plan through continuous coordination. However, according to the information provided, everything is going according to schedule so far.
At the Kőröshegy viaduct, the planned renovations will be completed with the replacement of the spans (but elsewhere, e.g. the Pentele bridge, the replacement of the spans will also start in September), and corrosion protection works are ongoing at the M7 viaduct during the closure.
At the time of the bridge closure, those arriving from Budapest will have to leave the track at the Zamárdi Upper/Siófok West junction and return at Balatonszárszó. Drivers coming from the border have to leave the track at Balatonszárszó junction and re-join the track at Zamárdi felső/Siófok west.
Source : Link
-
Bound track 2026. 10. 07.
Aurora beneath the Apennines – Another tunnel is being built on the Naples–Bari railway line
-
Road building 2026. 10. 13.
A consortium comprising STRABAG and Duna Aszfalt has been awarded the contract to build the North Macedonian motorway
-
Current at 2026. 10. 05.
Sofitel Hotel is the only Hungarian project in the running for the Dalux Award 2026 award – Watch the video too!
-
What is being built? 2026. 10. 09.
One of Budapest’s oldest nurseries is being renovated whilst preserving its timber roof structure