Road building
Esztergom's roads could improve a lot
The Esztergom Local Government has ordered the stabilisation of several roads, the renovation of the steps of the Basilica and the Stations of the Cross, as well as the construction of a sewage network on Magyary László Street, at a net cost of HUF 2.5 billion framework agreement worth a net value of HUF 2.5 billion, which was awarded to C-Sped 84 Kft. and STR Mély- és Magasépítő Kft..
Renovation of the basilica staircase and the downtown Calvary stairs
Earth and rock excavations include
- the scrub next to the stairs will be cleared 300 m2-en,
- to the new pavement 134,79 m3 lifting of the soil in the paved area by hand is required,
- and for the repair of the subgrade under the pavement, 46,08 m3 in quantity.
Stabilisation of broken roads
The winners will have to repair the gravel roads of Esztergom in several locations; in several places they will have to prepare a new, stable road surface by spreading a bitumen emulsion layer, together with the necessary drainage works, so that
- in Széchy Dénes street,
- on Duna street,
- in Oltóssy street,
- in the cemetery street,
- in Zamárd street,
- in Rétkerti-Cseresznyés street and
- in the Border Street.
Construction of wastewater network in Magyary László street
The contractor will be responsible for the construction of a sewer network (backbone network + house connections) along a length of approximately 300 metres on László Magyary Street in Esztergom. The new backbone sewer is planned to connect 15 residential properties. This will involve the restoration of the grass verge and the grass verge above it on the left bank of the St George's Ditch, including the removal of 20 metres of the bank railing.
Source : Link
-
Bound track 2026. 10. 07.
Aurora beneath the Apennines – Another tunnel is being built on the Naples–Bari railway line
-
Road building 2026. 10. 13.
A consortium comprising STRABAG and Duna Aszfalt has been awarded the contract to build the North Macedonian motorway
-
What is being built? 2026. 10. 09.
One of Budapest’s oldest nurseries is being renovated whilst preserving its timber roof structure
-
Current at 2026. 10. 10.
„The focus will not be on Lean’s equipment, but on how we operate” – the ‘Lean in the Construction Industry’ conference in November