The countdown has begun: another section of the M6 motorway will soon be open for traffic 

Published

The trial operation and the technical handover procedure are already underway on the final section of the M6 motorway. The project will complete the Hungarian section of the TEN-T corridor between the Adriatic and the Baltic Sea. 

The contractor for the 20 km long section between Bóly and Ivánvárda is a consortium of STRABAG Építő Kft. and Duna Aszfalt Zrt., commissioned by Építési és Közlekedési Minisztérium. The motorway section, with a crown width of 26.6 metres, physical separation in the middle and a hard shoulder, will be built at a net contract value of HUF 88.6 billion.

The M6 is nearing completion

We have reported regularly on the work to extend the M6 motorway to the border. Most recently, in the early autumn, we reported that work had begun on the traffic engineering works.

According to the information we have received, by January the project had entered its final phase. Gábor Boldizsár, chief architect of Duna Aszfalt Zrt., told Magyar Építők that the construction of the missing asphalt pavements, dirt road connections and plant exits was completed in the autumn. The wildlife fences at the intersections were closed.

The paving of all traffic engineering devices (pavement markings, signs, barriers, light barriers) and the paving of the parking areas and pavements of the TSM (National System for Measuring the Weights of Vehicles) station for traffic safety was also completed. Gábor Boldizsár added that the reclamation of the areas affected by the works will be completed soon.

Roundabout, special level interchange, TSM station, special bridges built

The specialist pointed out that they had to solve a number of specific tasks. Of the 21km section, 11km of which were constructed by Duna Aszfalt Zrt., included a separate junction with a 2km access road and roundabout, a viaduct and several major structures. One of the most of these was a wildlife crossing of particular curvature and size.

In addition to the wildlife crossing, a major professional challenge was laying the railway bridge and coordinating the multiple tasks of the TSM station, which required a high level of contractor scheduling and organisation.

The technical handover has started

The chief architect of the Duna Aszfalt Zrt. told us what still needs to be done before the handover.
"We are in the process of completing landscaping, dismantling and removing temporary facilities, cleaning the pavements, and installing benches, waste bins and bicycle racks at the TSM station area."
Gábor Boldizsár also said that with the involvement of the future operators, the trial operation of the systems engineering, water purification technology, electrical and HVAC systems at the TSM station is already underway.

The technical handover procedure has started, after which the client, the Ministry of Construction and Transport (ÉKM) will initiate the procedures for the placing in service and operating licence with the competent authorities. Once the licensing process has been completed, the final section of the M6 motorway will be opened to traffic once the permits have been obtained.

The Hungarian section of the Adriatic-Baltic road link becomes complete

The extension of the M6 motorway to the border will also improve the transport infrastructure in the Danube-Main and Mohács regions. The development will also enable safe and rapid transit traffic between northern and southern Europe. The completion of the final section of the M6 will complete the Hungarian section of the TEN-T corridor linking the Adriatic and Baltic Sea regions by road.