Road building
The bank closure on the new Danube bridge is completed, and the link between the Paks and Kalocsa banks is established
The construction project of the new Danube bridge Duna Aszfalt Zrt. in the Paks and Kalocsa region has reached an important moment. According to our newspaper, on 26 January, the last deck slab (MM20) was poured on the embankment bridge of the almost 1 km long, three-part structure (two floodplain bridges and the embankment bridge between them).
The track record has become continuous
On the bridge, which is being built under the Építési és Közlekedési Minisztérium project, the left-bank floodplain bridge and the right-bank floodplain bridge were closed on Friday after the middle span bridge was placed in place, thus making the deck continuous.
"Today, the connection between the left and right banks of the Danube has been effectively established by the Kalocsa-Paks Danube bridge," the report sent to our newspaper reads.
The summing up of Friday's event was that the final static framework was essentially in place, which will serve as a crossing over the Danube river for at least 100 years after the handover, taking into account the design lifetime of the bridge structures.
These are the tasks still to be completed by the contractors
But the work is far from over: the dressing of the bridge is about to begin. This will include the application of the coating systems protecting the structures, the installation of the railings and stormwater drainage systems, and the installation of the bridge monitoring system.
According to the schedule, the technical handover of the bridge will take place at the end of spring, after which the crossing will be opened to traffic.
The summary concluded by recalling that since the delivery of the worksite in 2021
- 2222 metres of 1.5 metre diameter piles were drilled to form the foundation of the bridge,
- 28,000 m3 of concrete was used in the bridge,
- Over 5,000 tonnes of steel structures have been fabricated and installed, representing more than 40 km of certified welded seams,
- 418 km of extradosed and internal tension cables were installed,
- 82,300 tonnes of hydraulic engineering stone were installed as river control and pillar protection.
Source : Link
-
Road building 2026. 10. 13.
A consortium comprising STRABAG and Duna Aszfalt has been awarded the contract to build the North Macedonian motorway
-
What is being built? 2026. 10. 09.
One of Budapest’s oldest nurseries is being renovated whilst preserving its timber roof structure
-
Current at 2026. 10. 10.
„The focus will not be on Lean’s equipment, but on how we operate” – the ‘Lean in the Construction Industry’ conference in November
-
Bound track 2026. 10. 08.
Déli railway station is set to undergo a major refurbishment, paving the way for double-decker trains