Road building
A renewed track for motorists on the M6 by autumn
The renovation of the M6 and M8 motorways has been ongoing for over a year, since May 2023. The contractor, SWIETELSKY Magyarország Kft. will complete the work on the M6 Duna Motorway Concession Ltd project by the agreed deadline of the end of October 2024.
The project involves major maintenance and resurfacing works on the section of the M6-M8 motorway between Érdi-tető - Dunaújváros between sections 54+000 - 76 + 200 km on the M6, and between sections 73 + 750 - 78 + 300 km on the M8.
As we learned from Tamás Kovács, project manager, the SWIETELSKY Magyarország Kft.'s tasks include
- resurfacing of the Szentmihály rest area and the Dunaújváros complex rest area,
- pavement rehabilitation of 6 motorway junctions (Adonyi junction, Kulcsi junction, Dunaújváros - Észak junction, Dunaújváros-Centrum junction, M6-M8 motorway junction, M8 - junction of the 6th main road), and
- resurfacing of 10 underpasses (national roads and dirt roads crossing the motorway) on the section.
A total of around 820 000 sq m of pavement on motorways, junctions, rest areas and structures will be resurfaced under the contract. This will involve the paving of 90 000 tonnes of asphalt.
Project off to a flying start
The construction works started in early May 2023, last year's target was to reach 30% completion, and the company has successfully completed these large volume works with built-up traffic diversion. By the end of the year, most of the M8 motorway section closed to traffic, the M6-M8 motorway junction, both sides of the Szentmihály rest area, most of the Dunaújváros complex rest area, 9 underpasses and the M6 motorway between sections 71+100 - 76+200 km had been renewed.
Keeping to the timetable
After the winter shutdown, large-scale resurfacing work resumed in April 2024. So far, 230 000 m2 of pavement have been resurfaced and two junctions - Adonyi and Dunaújváros-Necs - have been completely renewed. (The photos were taken during the asphalting of the Dunaújváros-Necs junction and the paving of the Adonyi junction). Currently, work is underway on the Dunaújváros Centrum junction and the Újvárosi complex rest area on the Pécs side. This will be followed by the Kulcsi junction area.
The project manager also informed us that the renovation will mainly involve replacing the wearing course, but in technically justified places, the binder course and base course will also be replaced.
The contractor will have a detailed schedule for the completion of the project by the end of October. For traffic management and technical reasons, the 22 kilometres of the M6 have been divided into 13 diversion stages, and each section will be progressed accordingly.
The reconstruction of a motorway in traffic is subject to constraints
The construction schedules and the necessary temporary traffic diversion plans will also be prepared by SWIETELSKY, with the approval of the client as the road manager.
"A section of motorway is usually implemented in two traffic management phases. First the passing and passing lanes are built and traffic flows in the previous lane, then the previous lane is built and traffic flows in the new passing lane by "reversing" the traffic flow.
The biggest challenge is that we work on a busy motorway, which is much more constrained than a traditional "closed" workspace"
- added Tamás Kovács, project manager.
Extraordinary efficiency achieved with new asphalt mixing plant
As reported in our newspaper, the SWIETELSKY Magyarország new asphalt mixing plant in Székesfehérvár was completed in the spring. The facility enables the production of hot mix asphalt with more economical energy consumption and the recycling of 40 per cent of the asphalt milled during road renovations.
The high-capacity plant has a production capacity of 210 tonnes per hour and will fully meet the asphalt needs of the project in question, putting the construction on a firm footing. Work in 2023 will be serviced by the former unit on the same site, while this year's needs will be met entirely by the new plant.
Source : Link
-
Bound track 2026. 10. 07.
Aurora beneath the Apennines – Another tunnel is being built on the Naples–Bari railway line
-
Road building 2026. 10. 13.
A consortium comprising STRABAG and Duna Aszfalt has been awarded the contract to build the North Macedonian motorway
-
What is being built? 2026. 10. 09.
One of Budapest’s oldest nurseries is being renovated whilst preserving its timber roof structure
-
Current at 2026. 10. 10.
„The focus will not be on Lean’s equipment, but on how we operate” – the ‘Lean in the Construction Industry’ conference in November