Road building

Transport and public space renewal in the XIII district: new roads and bridges built, green spaces restored

Published

Photos by Erdei MIhály/magyarepitok.hu
The SWIETELSKY Magyarország Kft. development aims to contribute to improving the quality of life of the district's residents through sustainable transport solutions and a quality urban environment.

At the beginning of June, the 13th District Local Government launched a large-scale development project aimed at renewing its transport and public service infrastructure using its own resources. The investment, worth a net HUF 2.8 billion, is being carried out on behalf of the Local Government of Budapest's 13th District. The investment, worth a net HUF 2.8 billion, is being carried out on behalf of the Local Government of Budapest's 13th District. The project is being implemented by https://magyarepitok.hu/temak/swietelsky-magyarorszag-kft rel="noopener">SWIETELSKY Magyarország Kft., which won the open public procurement procedure. The development is taking place on Cserhalom Street, between Vizafogó Street and Meder Street, and aims to significantly improve the daily transport and quality of life of city residents. The construction period is two years.

Photos by Mihály Erdei/magyarepitok.hu

One of the highlights of the project is the development of the transport network. The new road, which will be around 730 metres long, will have a modern divided carriageway design to make traffic safer. In addition, three new roundabouts, two rebuilt road junctions and two signalised cycle path crossings will ensure connectivity and comfortable travel.

A more liveable environment, safer transport

In addition to the new transport network, the development of green spaces will also play an important role. More than 270 new trees will be planted and the green spaces around the roads will be renewed, with more than 4 000 m² of shrubs and 12 500 m² of grassland. The area will also feature 132 new pieces of street furniture, including benches, tables, seating and a fenced dog run, as well as a state-of-the-art agility track with various obstacles for the four-legged friends.

The project will also include a modern, active recreation park with outdoor fitness equipment for all ages, accessible to all.

The old bridges over the Rákos stream on Cserhalom street will be replaced by two brand new crossings. The project will involve the construction of two identical prefabricated beam bridges, each with a span of 18 metres and an overall width of 13.62 metres. The width of the carriageway will be 7.5 m to ensure uninterrupted road traffic. The development aims to improve road safety and traffic permeability in the area.

Utility networks are also being renewed

Public services will also be upgraded, with new stormwater drains and new catchments for rainwater run-off, and the renewal of district heating pipes. The project will also include the demolition of the district heating distribution structure and the relocation of the district heating pipelines, ensuring modern and sustainable energy solutions.

The street lighting will also be modernised: around 80 10-metre-high chandeliers in the area will be replaced. Improvements to the transport power supply are also part of the project, which includes the replacement of E.on's underground cables and the relocation of communication cables.

The aim of the project is to ensure that the transport, public services and green spaces of this dynamic urban area meet all the needs of the 21st century. Improvements will be made to ensure sustainability, transport safety and improve the quality of urban life, while at the same time ensuring the comfort and safety of residents. The public will be kept informed about the works.